I am developing an Excel project scheduler that mimics some Microsoft Project functionality. If the user enters Start and Finish dates, it uses NETWORKDAYS to calculate Duration based on Start and Finish dates. Similarly, if the user enters Start and Duration, it uses WORKDAY to calculate a Finish date based on Start and Duration. (This is implemented in VBA, so it detects which two values the user has entered.)
The problem is that the functions aren't consistent.
Start Finish Duration calculated with NETWORKDAYS Finish recalculated using WORKDAY Wed 10/1/2014 Thu 10/2/2014 2 Fri 10/3/2014
Am I simply incorrectly interpreting the specs for these two functions? I can certainly fudge the results by adding or subtracting 1 here and there but I would rather make sure I understand how they're supposed to work. (I have never been impressed with the rigor of Microsoft's documentation of Excel functions but that is a discussion for another day.)