Hi,
I'm looking to forecast 2 scenarios as follows for a project:
Start Date: 07/06/15
End Date: 12/31/15
PO Cap: $125,000
I have an example attached.
I would like to assume standard work hours & holidays & allocate available work hours between these days, as well as distribute or allocate the PO Cap evenly between start & end dates?
2nd Scenario,
Same as above but have the option to Front load by 1/4, 1/2 or 3/4 so it's more representative of a real world project.
Thanks for the assistance.
Bookmarks