+ Reply to Thread
Results 1 to 9 of 9

Time & PO Cap Distribution or Allocation

  1. #1
    Valued Forum Contributor
    Join Date
    07-16-2007
    Location
    GA
    MS-Off Ver
    Office 365 - Version 2403
    Posts
    1,054

    Time & PO Cap Distribution or Allocation

    Hi,

    I'm looking to forecast 2 scenarios as follows for a project:

    Start Date: 07/06/15
    End Date: 12/31/15
    PO Cap: $125,000

    I have an example attached.

    I would like to assume standard work hours & holidays & allocate available work hours between these days, as well as distribute or allocate the PO Cap evenly between start & end dates?

    2nd Scenario,

    Same as above but have the option to Front load by 1/4, 1/2 or 3/4 so it's more representative of a real world project.

    Thanks for the assistance.
    Attached Files Attached Files
    MyCon
    -- Using Latest Version of Excel

  2. #2
    Valued Forum Contributor
    Join Date
    09-17-2012
    Location
    Johannesburg, South Africa
    MS-Off Ver
    Excel 2007
    Posts
    454

    Re: Time & PO Cap Distribution or Allocation

    Scenario 1:
    Format D20:AB20 and D20:AB20 as numbers.

    hours_po_distribution_cy.xlsm

    Enter this formula in D18 and copy across:
    Formula: copy to clipboard
    Please Login or Register  to view this content.


    Enter this formula in D20 and copy across:
    Formula: copy to clipboard
    Please Login or Register  to view this content.


    Please explain what you mean by 'front load'.

  3. #3
    Valued Forum Contributor
    Join Date
    07-16-2007
    Location
    GA
    MS-Off Ver
    Office 365 - Version 2403
    Posts
    1,054

    Re: Time & PO Cap Distribution or Allocation

    Hello cyiangou & Others,

    Thanks for taking the time to assist.


    This is almost what I'm looking for, however for my Hours Distributed row or row 19, I'm looking to distribute or allocate the cumulative total available (planned) hours during specified Start & End Dates.

    For example if I have a 2 week work duration & assuming normal work week 0r 40 hours, then I would have 80 hours or 40 hours distributed / allocated per week over 2 weeks. If one week falls on a holiday, then I would have 8 hours less because of this.

    Now, I'm looking to do the same except over a much longer duration.

    The PO Cap Distributed appears exactly what I'm seeking - Taking the PO Cap & distributing / allocating over the specified Start & End Dates.

    As for "Front Loading" - I'm creating this for a project. With most projects, the majority of work effort is "up front" then approximately midway through to 3/4 into the project, it tappers down or less effort is needed.

    I'm looking to demonstrate this by putting 1/4 (.25) , 1/2 (.5) or 3/4 (.75) option in & distributing / allocating that across.

    I modified your file to include this in a box area called "Front Load Effort Distribution".

    Thanks again for the assistance
    Attached Files Attached Files

  4. #4
    Valued Forum Contributor
    Join Date
    09-17-2012
    Location
    Johannesburg, South Africa
    MS-Off Ver
    Excel 2007
    Posts
    454

    Re: Time & PO Cap Distribution or Allocation

    ...however for my Hours Distributed row or row 19...
    Surely D19 copied across should just be:
    Formula: copy to clipboard
    Please Login or Register  to view this content.

  5. #5
    Valued Forum Contributor
    Join Date
    07-16-2007
    Location
    GA
    MS-Off Ver
    Office 365 - Version 2403
    Posts
    1,054

    Re: Time & PO Cap Distribution or Allocation

    Hi cyiangou & Others,

    The , "=D18*8" works well - Thanks for this.

    What's the way to get the PO Cap Distributed / allocated between specified Start & End Dates.

    As for "Front Loading" - I'm creating this for a project. With most projects, the majority of work effort is "up front" then approximately midway through to 3/4 into the project, it tappers down or less effort is needed.

    I'm looking to demonstrate this by putting 1/4 (.25) , 1/2 (.5) or 3/4 (.75) option in & distributing / allocating that across.

    Thanks

  6. #6
    Valued Forum Contributor
    Join Date
    09-17-2012
    Location
    Johannesburg, South Africa
    MS-Off Ver
    Excel 2007
    Posts
    454

    Re: Time & PO Cap Distribution or Allocation

    Don't you also need to specify an up-front amount? eg. During the first 6 months allocate 80% of the budget, in the remaining 18 months, consume the rest.

  7. #7
    Valued Forum Contributor
    Join Date
    07-16-2007
    Location
    GA
    MS-Off Ver
    Office 365 - Version 2403
    Posts
    1,054

    Re: Time & PO Cap Distribution or Allocation

    Hi cyiangou

    I think we have kind of the same intent.

    From my perspective, I was taking the PO Cap or budget & trying to demonstrate that during the first 1/4 of the project - Where a large part of the planning takes place may take up to 1/4 to half the budget during the 1/2 of the program duration, then express that in dollars?

    Is this making sense? This may be a little more complex to demonstrate but as we probably know with projects, majority of funds are spent up front with a burn down until funds are used up or if going the opposite way - A burn up rate until the budget rate meets or exceeds PO cap.

    For the first part of my PO Cap - Simply showing an even distribution or allocation over the specified duration is sufficient - Even though it it's not realistic for the last 3/4 to end of program because the weekly money spent should be decreased.

    I hope this make sense.

    Thanks again for the assistance.

  8. #8
    Valued Forum Contributor
    Join Date
    07-16-2007
    Location
    GA
    MS-Off Ver
    Office 365 - Version 2403
    Posts
    1,054

    Re: Time & PO Cap Distribution or Allocation

    Hi Group,

    Does anyone have a suggestion?

    How to take PO Cap or limit & distribute over specified dates - Assuming Standard Work & excluding holidays

    Example: $150K between July 6, 2015 through December 31, 2015


    Thanks

  9. #9
    Valued Forum Contributor
    Join Date
    09-17-2012
    Location
    Johannesburg, South Africa
    MS-Off Ver
    Excel 2007
    Posts
    454

    Re: Time & PO Cap Distribution or Allocation

    I suggest you add an additional row to contain factors of 1. All factors summed across all periods must equal 1.

    To start, put a factor of 1/(number of periods) in each cell multiplied by the PO cap. This will give you a flat distribution of funds.

    Now you can play with different distribution profiles, front loading, inverted bathtub, even sinusoidal if you're feeling silly. Just ensure all your factors add up to 1.

+ Reply to Thread

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Similar Threads

  1. Distribution over Time
    By cowboyphil in forum Excel Formulas & Functions
    Replies: 0
    Last Post: 04-14-2015, 01:26 PM
  2. A graph showing normal distribution over Time variable
    By resvic in forum Excel Charting & Pivots
    Replies: 13
    Last Post: 02-11-2015, 05:09 PM
  3. Seat allocation with Date & Time
    By jayexcel1 in forum Excel Programming / VBA / Macros
    Replies: 7
    Last Post: 04-10-2014, 11:44 AM
  4. [SOLVED] Time Allocation
    By blue5ky in forum Excel Formulas & Functions
    Replies: 10
    Last Post: 12-05-2013, 06:39 PM
  5. Excel 2010 - Project Day Allocation, Time Spent Calculation
    By craigj21 in forum Excel Formulas & Functions
    Replies: 0
    Last Post: 08-27-2013, 07:20 AM
  6. Replies: 2
    Last Post: 02-04-2011, 03:36 AM
  7. Hour Allocation over time
    By johnuw in forum Excel General
    Replies: 0
    Last Post: 02-13-2005, 01:15 AM

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts

Search Engine Friendly URLs by vBSEO 3.6.0 RC 1