+ Reply to Thread
Results 1 to 7 of 7

Percentage doesn't add up

  1. #1
    Registered User
    Join Date
    08-11-2005
    Posts
    5

    Angry Percentage doesn't add up

    Hi,
    I got a problem with a planning tool I've built to show how many extra sales are needed each month by my teams to hit a target and then an overachieveing target.

    I've also applied a weighting to each team to allow for experience. My problem occurs when I then try to add the overachieveing target (eg. 12%) and then apply the weighting to each team, every result is only 96.44% of what I expected it to be.

    The sum I'm using to calculate each teams stretched target is
    =sum(stretched plan number of sales*team size as a percentage of total staff)*(1+weighting applied to that team, which is also a percentage)

    Please help!

  2. #2
    Forum Contributor
    Join Date
    03-13-2005
    Posts
    6,195
    I cannot get the answer that you show.

    Assuming 3 groups (to test) of 2 people, 2 people and 6 people in a total staff of 10, and assuming total plan sales of 20

    The first portion "stretched plan number of sales*team size as a percentage of total staff" would show 4 and 4, and 12 for the larger group.
    The second portion "1+weighting applied to that team, which is also a percentage" would equate to 1.12 for a 12% increase.

    4 * 1.12 = 4.48 (twice) and 6 * 1.12 = 13.44

    4.48 + 4.48 + 13.44 = 22.4, the same figure as the original figure of 20 times 1.12

    Hope you can spot your error from that.




    Quote Originally Posted by Homer J
    Hi,
    I got a problem with a planning tool I've built to show how many extra sales are needed each month by my teams to hit a target and then an overachieveing target.

    I've also applied a weighting to each team to allow for experience. My problem occurs when I then try to add the overachieveing target (eg. 12%) and then apply the weighting to each team, every result is only 96.44% of what I expected it to be.

    The sum I'm using to calculate each teams stretched target is
    =sum(stretched plan number of sales*team size as a percentage of total staff)*(1+weighting applied to that team, which is also a percentage)

    Please help!

  3. #3
    Registered User
    Join Date
    08-11-2005
    Posts
    5
    Thanks for your reply but I have a question
    6 * 1.12 = 13.44
    Sholdn't this be 6.72 & then the numbers dont add up???

  4. #4
    Forum Contributor
    Join Date
    03-13-2005
    Posts
    6,195
    Sorry, quoted wrong number, 2, 2 and 6 people with 20 sales = 4, 4 and 12

    12 * 1.12 = 13.44



    Quote Originally Posted by Homer J
    Thanks for your reply but I have a question


    Sholdn't this be 6.72 & then the numbers dont add up???

  5. #5

    Re: Percentage doesn't add up

    Homer J wrote:
    > I got a problem with a planning tool I've built to show how many extra
    > sales are needed each month by my teams to hit a target and then an
    > overachieveing target.


    A specific example with hypothetical values might facilitate the
    discussion. And it might be better to provide actual Excel or other
    mathematical formulas instead of English descriptions. That latter is
    usually not sufficiently precise.

    > I've also applied a weighting to each team to allow for experience. My
    > problem occurs when I then try to add the overachieveing target (eg.
    > 12%) and then apply the weighting to each team, every result is only
    > 96.44% of what I expected it to be.
    >
    > The sum I'm using to calculate each teams stretched target is
    > =sum(stretched plan number of sales*team size as a percentage of total
    > staff)*(1+weighting applied to that team, which is also a percentage)


    Please clarify ....

    Is the "stretched plan number of sales" the same as the "overachieving
    target"? That is, it already incorporates (e.g) the 12% factor for
    "overachieving". No need to multiply anything by 1.12, as one
    respondent
    did. Right?

    Is the "weighting applied to that team" the same as "the weighting ...
    to allow for experience"? And is it "then applied" __after__ the
    overachieving factor (12%, e.g)? That is, the weighting factor is
    different for each team, and it is unrelated to (e.g) the 12%
    overachieving factor. Thus, we would not use 1.12 in place of the
    "1 + weighting applied to that team", as one respondent did. Right?

    If my first assertion is correct, what are you summing and why? I
    would think an individual team's base overachieving target (before
    weighting) is simply "stretched plan number of sales * team size /
    total sales staff size".

    And if you are summing (only) all of the accounts that team is
    responsible for, why would you multiple my the team's size as a
    proportion of the total sales staff?

    Moreover, the description "1 + weighting ... as a percentage" does
    make sense to me. I suspect you should to remove "1 +". But that
    is based on the ***-u-me-tion that the "weighting ... to allow for
    experience" means that a weak team would have a weighting factor
    less than one (80%, e.g).

    As for an explanation of the 3.56% error (1 - 96.44%), I cannot help
    you, since you did not provide sufficient information, even
    hypothetically.


  6. #6
    Registered User
    Join Date
    08-11-2005
    Posts
    5
    Sorry if I made this sound confusing.
    This is what I'm trying to do. I have a plan for the whole business and a number of teams working towards that plan. None of the team have the same level of experience so I'm trying to add a weighting to each team. Then work out what percentage of the workforce each team is. Then split the whole plan by the percentage for each team and then add the weightings to each team.
    The stretched plan & over acheiveing plan are the same thing, that just me getting mixed up in my own terminology. It all goes wrong when I add the weightings

    I've attached the spreadsheet I've made if its any help.
    The top part is the basic plan split out between each team. The middle part adds on the stretched target. The bottom part applys the weighting. The total of the weighted section should equal the stretched plan. My problem is it doesn't.

    I really appreciate your help with this.
    Attached Files Attached Files

  7. #7

    Re: Percentage doesn't add up

    Homer J wrote:
    > I've attached the spreadsheet I've made if its any help.
    > [....]
    > +-------------------------------------------------------------------+
    > |Filename: Planning Test.xls.zip |
    > |Download: http://www.excelforum.com/attachment.php?postid=3692 |
    > +-------------------------------------------------------------------+


    I was not able to access the spreadsheet. I will
    offer my own interpretation and examples. I hope
    they are in line with what you are trying to do.
    If not, perhaps you could fine-tune my examples by
    substituting numbers of your own.

    As I understand it, you have a target sales goal (S),
    which you nominally distribute to each sales team
    based on the proportion of the team size (t[i]) to
    the total sales staff (T). Thus, nominally, a team's
    sales target is s[i] = S*t[i]/T. As a check, I expect
    T = SUM(t[i]).

    However, in deference to the strengths and weaknesses
    of each team, you apply a weighting factor (w[i]) to
    each team's goal. Consequently, the team's actual
    sales target is s[i] = S*w[i]*t[i]/T. As a check, I
    expect that S = SUM(S*w[i]*t[i]/T).

    I suspect your problem is in the choice of weights.
    I will explain below. But first ....

    Note-1: For the purposes of this problem, it does
    not seem to matter that the target sales goal (S) is
    actually an "overachieving" goal, for example 12% over
    expected sales. That fact might affect some of your
    own thinking, for example your choice of individual
    weights (w[i]). But it does not seem to have any
    bearing on the formulas here.

    Note-2: Notation like t[i] is my way of indicating
    subscripts. If you are not comfortable with such
    formal notation, you can think of t[i] as cell names
    T1, T2 or $T$1, $T$2 etc. The values S and T might
    be constants; or (better) they might be references to
    other cells, for example A1 and B1 or cells named
    "Sales" and "Team".

    I think the key is: you must choose weights such
    that T = SUM(w[i]*t[i]). This is derived from the
    "S = SUM(...)" check above.

    It can be tricky to ensure T = SUM(w[i]*t[i]). The
    easiest way might be to set up a column with
    "w[i]*t[i]" in each cell, and experiment with values
    of w[i] until the total of the column is T.

    Consider the following example:

    t[i] = { 2, 3, 4, 5, 6}, T = 20
    w[i] = {??, 1, 1, 0.8, 1}

    What should w[1] be for t[1] (2 people)?

    The answer is 1.50. In this simple case, it can be
    computed as w[1] = (t[1] + t[4] - w[4]*t[4]) / t[1].

    That is, if you believe that team #4 can achieve only
    80% of its goal and teams #2, 3 and 5 can achieve
    only 100% of their goals, team #1 must pick up the
    slack by achieving 150% of its goal.

    More commonly, you might expect more than one team to
    cover the slack of one or more teams -- if that is
    possible. For example, if the total sales goal S is
    100:

    t[i] = { 2, 3, 4, 5, 6}, T = 20
    w[i] = {1.04, 1.04, 1.05, 0.8, 1.1}
    s[i] = {10.4, 15.6, 21, 20, 33}, S = 100

    This can be very tedious to do if you have a large
    number of teams. You probably cannot set up a formula
    in every w[i] cell like the one for w[1] above. You
    are likely to get "circular references" errors, unless
    you can make some simplifying assumptions in some w[i]
    cells.

    Good luck! I hope this helps you uncover the source
    of your numerical error.


+ Reply to Thread

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts

Search Engine Friendly URLs by vBSEO 3.6.0 RC 1