    Graphing Work Job Periods over next three years

    Hi,

    My associates have jobs to do over the next three years. Each job is approximately 6 months long and they have about 70 each. I have inputted each job into excel as follows:

    Job Name Start Date Completion Date Worker
    San Fran-PM 1-Oct-2016 31-Mar-2017 Sarah
    Ithica-FM 1-Dec-2015 31-May-2016 Jim
    etc.

    I want to show on a graph the concentration of jobs over the next three years so that visually we can look and see how busy each associate will be. I'm thinking it may be best to show a timescale with time on the x axis, and then somehow plot each job. In any given month, each associate of course will be in the middle of several jobs. For example, Sarah may be working on, say, 20 jobs (some just starting and some nearing completion) and Jim may be working on 14.

    I'm at a loss on how to show this visually. The purpose of the graph is to see who is busiest in each month/year over the next three years.

    Thanks.

    CF

  2. #2
    Forum Guru Kaper's Avatar
    Join Date
    12-14-2013
    Location
    Warsaw, Poland
    MS-Off Ver
    most often: Office 365 in Windows environment
    Posts
    8,613

    Re: Graphing Work Job Periods over next three years

    Probably good idea will be to list days in this period and then use COUNTIFS to count jobs, which on given date already started + not finished yet + are assigned to given person like:
    Formula: copy to clipboard
    Please Login or Register  to view this content.

    see attachment
    Attached Files Attached Files
    Best Regards,

    Kaper

  3. #3
    Registered User
    Join Date
    07-21-2015
    Location
    Vancouver, BC
    MS-Off Ver
    7
    Posts
    2

    Re: Graphing Work Job Periods over next three years

    Genius! Thanks so much!

  4. #4
    Forum Guru Kaper's Avatar
    Join Date
    12-14-2013
    Location
    Warsaw, Poland
    MS-Off Ver
    most often: Office 365 in Windows environment
    Posts
    8,613

    Re: Graphing Work Job Periods over next three years

    Glad to hear that
    If that takes care of your original question, please select Thread Tools from the menu link above and mark this thread as SOLVED.
    Thanks.

+ Reply to Thread

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Similar Threads

  1. Replies: 4
    Last Post: 07-06-2015, 05:56 PM
  2. Work Distribution between periods
    By Jdnethaji in forum Excel General
    Replies: 0
    Last Post: 11-03-2014, 10:22 AM
  3. Help with Calculating/Graphing Avg Server Process Cycle Time - Excluding Idle Periods
    By kr4z33ch3m15t_78 in forum Excel Formulas & Functions
    Replies: 1
    Last Post: 02-05-2013, 05:55 AM
  4. Replies: 1
    Last Post: 08-11-2012, 05:43 PM
  5. Repeating time periods - (when simple MOD doesn't work)
    By joeljoel in forum Excel General
    Replies: 3
    Last Post: 08-10-2011, 10:05 AM
  6. Excel 2007 : Graphing RANGE of data along with individual years
    By richardlarson87 in forum Excel General
    Replies: 0
    Last Post: 08-01-2011, 09:58 PM
  7. Replies: 3
    Last Post: 03-09-2009, 09:00 AM

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts

Search Engine Friendly URLs by vBSEO 3.6.0 RC 1