    Post Switch dates/week numbers

    Hi,

    I have a chart that I use as a process plan to building construction. It shows bars controlled by a start date and a length defined by number of working days. Right now the x axis shows by usual calendar dates (see image below) but I'd like to be able to somehow switch it to week numbers.

    chartex.PNG

    I tried to convert the dates with the WEEKNUM formula and then add those data to the chart but it doesn't really work if I want to show a more than 2 years period: it shows 1 to 53 (week in a year) instead of 1 to 53 to 1 to 53 again etc..

    I think what I want is to change what is displayed by the x axis as well as its "graduations", show a vertical line every 1/2/3 weeks depending on the "zoom". I also thought about maybe doing to charts and hiding/showing the one I want with a button and a macro, but that's not really the place for that question.

    Any suggestions?

    Thanks.

    David

  2. #2
    Forum Expert
    Join Date
    08-16-2015
    Location
    Antwerpen, Belgium
    MS-Off Ver
    2007-2016
    Posts
    2,380

    Re: Switch dates/week numbers

    Maybe convert to weeknum and year, 1-2017 .....


    Kind regards
    Leo

  3. #3
    Registered User
    Join Date
    08-24-2017
    Location
    DK
    MS-Off Ver
    Microsoft Office Professionel Plus 2010
    Posts
    2

    Re: Switch dates/week numbers

    I did with that formula: =(WEEKNUM(A1;2)&"-"&YEAR(A1)
    But it doesn't do anything once put in a chart...Besides I don't think this is very "safe", this year (2017) the 1st week starts the 2nd of January so the whole thing is offset by one week, excel count 01-01-2017 as being the week 1, and so week 2 is from 02-01...

+ Reply to Thread

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Similar Threads

  1. [SOLVED] Count Week numbers given start and finish week number
    By Vassen in forum Excel Programming / VBA / Macros
    Replies: 12
    Last Post: 09-30-2016, 01:59 AM
  2. Using a Switch Case with logic operators on dates
    By biguel in forum Excel Programming / VBA / Macros
    Replies: 2
    Last Post: 03-08-2016, 02:16 PM
  3. Convert Dates to 2 Digit Week Numbers
    By papageorgio in forum Excel Programming / VBA / Macros
    Replies: 2
    Last Post: 05-29-2015, 09:33 PM
  4. [SOLVED] Counting how many dates in a range fall into this week and last week
    By AneelK in forum Excel Formulas & Functions
    Replies: 5
    Last Post: 01-08-2013, 09:38 AM
  5. Distribute dates by week numbers
    By excel90 in forum Excel General
    Replies: 4
    Last Post: 09-28-2010, 07:01 AM
  6. [SOLVED] RE: How do I switch off automatic formatting (e.g. dates)?
    By Vince in forum Excel General
    Replies: 0
    Last Post: 07-13-2006, 03:10 AM
  7. Replies: 1
    Last Post: 07-06-2006, 11:30 PM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts

Search Engine Friendly URLs by vBSEO 3.6.0 RC 1