I've been trying to wrap my head around making a legal calendar with a Gantt Chart. I've been using the Workday function to get it going and filling out the calendar but I can't get it lined up corretly with the court website. For Example, If under category I chose response, it should be 21 days after receiving. To test the calendar, The start date can be 11/21-11/25. If the start date is any of these days the due date should be December 24th. I've tried workday and I can't integrate Weekday function. Just gives me an error if I try to add to the function.
The Function I have is this:
=IF(C12="Initialized",1,IF(C12="Response",21+WORKDAY(11/1/2018,7,C35:C50),IF(C12="Demurrer",30+WORKDAY(11/1/2018,5,C35:C50),IF(C12="Received",1,IF(C12="Depo",14+WORKDAY(11/1/2018,5,C35:C50),IF(C12="",,))))))
So when I choose a category it will spit out a number of days, Then on the Chart it's this which is from Excel itself:
=IF(AND($C9="Received",H$5>=$E9,H$5<=$E9+$F9-1),2,IF(AND($C9="Initialized",H$5>=$E9,H$5<=$E9+$F9-1),1,""))
But I can't make the holidays work or weekends correctly. Any Help is appreciated