Percentage completion based on Today(Date)

  1. #1
    Registered User
    Join Date
    06-04-2014
    Posts
    3

    Percentage completion based on Today(Date)

    Hi,

    I have 5 columns :

    Column A : Start Date
    Column B : Finish Date
    Column C : Actual Start Date
    Column D : Actual Finish Date
    Column E : % Completion

    I want the formula for % completion based on Today Date in Column E.

  2. #2
    Forum Contributor pareshj's Avatar
    Join Date
    05-20-2014
    Location
    MUMBAI
    MS-Off Ver
    2007 & 2010
    Posts
    447

    Re: Percentage completion based on Today(Date)

    Hi,

    So do you want to calculate % completion on no. of days from start date?? Please clarify
    Click on "* Add Reputation" as a way to say thanks

  3. #3
    Forum Guru benishiryo's Avatar
    Join Date
    03-25-2011
    Location
    Singapore
    MS-Off Ver
    Excel 2013
    Posts
    5,147

    Re: Percentage completion based on Today(Date)

    welcome to the forum, shivamuniyappa. it would be nice if you can upload a sample excel file next time & also manually key in the results for a clearer picture. To upload, Click on GO ADVANCED and use the paperclip icon to open the upload window.
    View Pic
    and to illustrate your example better, click on How To Get Quick & Good Answers

    how do you determine % completion? for eg
    Actual Start is 4 Jun 2014. Actual Finish is 6 Jun 2014. today is 5 Jun 2014. what is the the %? is it 66.6%? 2 out of 3 days completed? if so, maybe;
    =IF(TODAY()<C2,0,(TODAY()-C2+1)/(D2-C2+1))

    Thanks, if you have clicked on the * and added our rep.

    If you're satisfied with the answer, click Thread Tools above your first post, select "Mark your thread as Solved".

    "Contentment is not the fulfillment of what you want, but the realization of what you already have."


    Tips & Tutorials I Compiled | How to Get Quick & Good Answers

  4. #4
    Registered User
    Join Date
    06-04-2014
    Posts
    3

    Re: Percentage completion based on Today(Date)

    What is the actual percentage completed based on current date against actual start date.

  5. #5
    Registered User
    Join Date
    06-04-2014
    Posts
    3

    Re: Percentage completion based on Today(Date)

    Thanks... I got it ....

+ Reply to Thread

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Similar Threads

  1. [SOLVED] Completion Percentage of a date range
    By Brian in forum Excel General
    Replies: 5
    Last Post: 09-08-2021, 06:55 AM
  2. [SOLVED] Conditional Formatting with Data Bars - Based on Completion Percentage
    By benwahchang in forum Excel General
    Replies: 9
    Last Post: 11-14-2014, 03:38 PM
  3. Replies: 4
    Last Post: 01-17-2013, 01:23 PM
  4. [SOLVED] Percentage based on the completion of the milestones
    By chriseverclear in forum Excel Formulas & Functions
    Replies: 2
    Last Post: 10-31-2012, 12:16 PM
  5. Calculation of a percent completion based upon due date
    By Anna Mainhart in forum Excel Formulas & Functions
    Replies: 2
    Last Post: 05-21-2012, 12:16 PM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts

Search Engine Friendly URLs by vBSEO 3.6.0 RC 1