Hi everyone, I need some help.
If I have different start and end dates and I need to calculate the amount that needs to be allocated every quarter say it starts on 28-Oct-15 (A187)and ends on 27-Feb-17 (B187) and i need to calculate the amount needed to bill in 2017Q4 (G2)
I have used the following and it does not work for those date starting in 2017
*E187 is the monthly cost.
=IF($G$2=MEDIAN($A187,$B187,$G$2),(3-MONTH($A187)+1)*$E187,0)
Please help