    I have "things" which should deliver a planned amount evenly over a start and end date. I am trying to use a weekly report date (which will change week to week) to calculate how many of those "things" should have been delivered over that time period.

    I figured out how to make it work if the weekly reporting period is completely outside/inside the time period, but cannot if only a few days fall into the star and end date.

    How can I calculate the number of days one date range overlaps another?
    Attached Files Attached Files
    Last edited by BryGuy81; 04-19-2017 at 01:16 PM.

  2. #2
    Registered User
    Join Date
    04-17-2017
    Location
    New York, USA
    MS-Off Ver
    2013
    Posts
    7

    Re: Calculate the portion of a planned number during a period, based on another time perio

    BryGuy81,

    Please take a look at the modified workbook attached.

    I've modified your formula in column G - using max to pick the higher of the report start date and Thing start date and min to pick the lower of the report end date and Thing end date to calculate only the overlapping days.

    Hope this solves your issue...let me know if something is unclear

    AK
    Attached Files Attached Files

  3. #3
    Registered User
    Join Date
    03-09-2016
    Location
    Los Angeles
    MS-Off Ver
    2014
    Posts
    15

    Re: Calculate the portion of a planned number during a period, based on another time perio

    Thank you so much, that worked!

  4. #4
    Registered User
    Join Date
    04-17-2017
    Location
    New York, USA
    MS-Off Ver
    2013
    Posts
    7
    Quote Originally Posted by BryGuy81 View Post
    Thank you so much, that worked!
    Great! Can you mark the thread solved if you have no further issue

+ Reply to Thread

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Similar Threads

  1. [SOLVED] Pivot Table : Planned and Actual Count Over Same Time Period
    By chullan88 in forum Excel Charting & Pivots
    Replies: 11
    Last Post: 02-11-2016, 12:44 AM
  2. [SOLVED] Calculate values based on time period
    By rtcwlomax in forum Excel Programming / VBA / Macros
    Replies: 58
    Last Post: 06-30-2015, 05:58 PM
  3. Calculate Time Period -
    By Matt1998 in forum Excel Formulas & Functions
    Replies: 1
    Last Post: 04-09-2014, 11:11 AM
  4. Replies: 1
    Last Post: 04-24-2013, 11:38 PM
  5. Replies: 30
    Last Post: 11-14-2012, 09:39 AM
  6. [SOLVED] Complicated:Calculate time period based on no. of units sold + fluctuations within period
    By omaha.crab in forum Excel Formulas & Functions
    Replies: 2
    Last Post: 09-06-2012, 03:04 AM
  7. Replies: 8
    Last Post: 02-23-2005, 06:58 PM

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts

Search Engine Friendly URLs by vBSEO 3.6.0 RC 1