    Help With Formula To Determine Interest Holding Cost for Development

    Hi there,

    I am trying to create a formula where I can determine the holding cost for a development I am doing based on the numbers below.

    Interest rate: 4.0%
    Term (months): 18
    Loan Amount: 1,238,350.00

    I am trying to create the formula as a template so I can use it into the future when looking to determine the potential holding costs on a development site. Where I can adjust the interest rate, term and amount based on the individual projects.

    I've searched up and down online with no luck so hoping someone here might be able to help me.

    Thanks in advance,
    Ben
    Attached Images Attached Images

  2. #2
    Forum Expert
    Join Date
    05-05-2015
    Location
    UK
    MS-Off Ver
    Microsoft Excel for Microsoft 365 MSO (Version 2402 Build 16.0.17328.20068) 64-bit
    Posts
    28,169

    Re: Help With Formula To Determine Interest Holding Cost for Development

    As an accounting ignoramus ... I don't know if the following will help ...


    http://www.driveyoursuccess.com/2011...ing-costs.html

  3. #3
    Forum Moderator - RIP Richard Buttrey's Avatar
    Join Date
    01-14-2008
    Location
    Stockton Heath, Cheshire, UK
    MS-Off Ver
    Office 365, Excel for Windows 2010 & Excel for Mac
    Posts
    29,464

    Re: Help With Formula To Determine Interest Holding Cost for Development

    Hi,

    With the Loan in A1, Annual Interest Rate % in A2 and number of months in A3 then use the formula

    Formula: copy to clipboard
    Please Login or Register  to view this content.


    The repayment of your 1,238,350.00 loan will be 1,314,794.09, i.e the interest is 76,444.09

    Or of course use the FV formula

    Formula: copy to clipboard
    Please Login or Register  to view this content.
    to get the 1,314,794.09 value
    Last edited by Richard Buttrey; 06-26-2017 at 05:15 AM.
    Richard Buttrey

    RIP - d. 06/10/2022

    If any of the responses have helped then please consider rating them by clicking the small star icon below the post.

  4. #4
    Registered User
    Join Date
    06-26-2017
    Location
    Australia
    MS-Off Ver
    15.22
    Posts
    2

    Re: Help With Formula To Determine Interest Holding Cost for Development

    Hi Richard,

    Thank you very much for you help, appreciated. It worked perfectly. I doubt I would have ever been able to work that out!

    Thanks again.

    Thanks also for your reply John, also very much appreciated.

+ Reply to Thread

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Similar Threads

  1. Phasing project development cost
    By OmarHamza in forum Excel Formulas & Functions
    Replies: 4
    Last Post: 03-08-2016, 10:06 AM
  2. Calculating interest only holding costs on a property for 'X' month period
    By Afrosupernova in forum Excel Formulas & Functions
    Replies: 2
    Last Post: 06-18-2015, 08:35 PM
  3. Replies: 0
    Last Post: 03-25-2014, 03:04 PM
  4. Replies: 10
    Last Post: 11-16-2012, 07:54 PM
  5. Stock holding cost
    By Aland2929 in forum Excel General
    Replies: 2
    Last Post: 09-11-2011, 08:34 AM
  6. Formula to determine Schedule cost
    By robert_shindorf in forum Excel General
    Replies: 2
    Last Post: 10-18-2008, 11:48 AM
  7. Annual Percentage Interest cost of discount not taken
    By Uli Hildebrand in forum Excel General
    Replies: 1
    Last Post: 07-25-2006, 12:50 AM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts

Search Engine Friendly URLs by vBSEO 3.6.0 RC 1