This spreadsheet is to be able to quickly see how many assemblies have been
built to date (Estimated Running Total) and have the Start Quantity
calculated based on what is left to build - divided by remaining project
weeks (each row) - while taking into consideration yield percentage.
For example:
Say I am at line 11.* It is telling me that 74 assemblies have been made
(out of 660).* We have scheduled to start another 40 assemblies expecting to
get 20 good assemblies based on the 50% yield.
Let's say that we had a good week, and instead of only 20 good assemblies
(50%), we got 30 good units (75%).
I want to be able to enter in 75% in B11 - have the Calculated Finish
Quantity (C11) update with the correct yield quantity (30) - and have the
Estimated Running Total update.
I then want (and this is the part I am having the most issue with) - line
A12 through line A40 update with new (equally divided based on remaining
build weeks left) Start Quantities based on a finished quantity of 660 and
taking into consideration the Yield Assumptions.
Bookmarks