Hi,
Please refer to the attached xls file.
Basically, I am setting up an Extension Of Time Register and need to find out the revised date for completion of an activity.
The cell I25 (Tab 1) currently works out the finish date from a physical commencement date as well as a project duration (taking into account a 6 day work week).
This is all good so far hopefully.
Now what I want to do, dependent on when the contract commences, I want it to take into account the public holidays and CPB days off that is showed in Tab 2.
(i.e, if the Contract, commences on 3/04/18 and is to be completed by 20/05/18, I want it to add to the formula in I25 these additional holidays. (i.e. Wednesday, 25 April 2018 and Monday, 7 May 2018) (as these are non work days and need to be added to the completion date)