Hi Guys,
I would greatly appreciate if you could support me to find a way of working for following issue.
I have downloaded Simple Gantt Chart template file. Screenshot 2019-08-01 at 23.01.29.png
As you can see from the screenshot it is working fine and when changing the status bar it is updating the chart, but I need to add another colour code using conditional formatting to show end date of the task is past, but still not completed it needs to be coloured as red from mentioned end date to current date (or =today().
Screenshot 2019-08-01 at 23.05.09.png
Above ise conditional formatting used in this sheet.
Blue = Not started
Green=Completed
Orange=today