Hi Guys,
I would greatly appreciate if you could support me to find a way of working for following issue.
I've downloaded Simple Gantt Chart template from MS Excel.
Template is working just fine. Bar chart is updated according to percent entered in status bar.
There are 2 colours representing the bar charts. Green (completed) & Blue (Not completed)
However, I need to add another condition to show overdue status. If the project is not completed by the given date, it should appear as red.
I have attached the sample sheet.
I would greatly appreciate if I can get hands on this please.
Thank you