    adding 15 workdays on the following month from a start date

    Hello,

    any assistance will be greatly appreciated.

    I need to get the 15th working day of the next following month of a start date.

    I figured it out but I have the formulas in two different cells to get my results. I used EOMONTH to get the end of the month of my start date +1 to get the first day of the next month, then i use another formula(WORKDAY) to get the 15th workday.

    I would like to combined both formulas in one cell and still get the same result. can this be possible? Thank you in advance.

    here is what i did,see attachment.
    15th working day.png

    A B

    1 START DATE 3/16/2020 formulas used YEAR HOLIDAYS
    2 4/1/2020 EOMONTH(B1,0)+1) 2019 1/1/2019
    3 15TH WORKDAY 4/22/2020 WORKDAY(B2,15,G2:G21) 1/21/2019
    2/18/2019
    HOW TO COMBINE THESE TWO FORMULAS IN ONE CELL TO GET THE SAME 5/27/2019
    RESULT OF B3? 7/4/2019
    9/2/2019
    10/14/2019
    WHAT I BASICALLY NEED IS THE 15TH WORKING DAY OF THE NEXT 11/11/2019
    FOLLOWING MONTH OF A START DATE 11/28/2019
    12/25/2019
    2020 1/1/2020
    1/20/2020
    2/17/2020
    5/25/2020
    7/3/2020
    9/7/2020
    10/12/2020
    11/11/2020
    11/26/2020
    12/25/2020
    Attached Files Attached Files

  2. #2
    Forum Expert
    Join Date
    02-10-2019
    Location
    Georgia, USA
    MS-Off Ver
    Office 365
    Posts
    2,831

    Re: adding 15 workdays on the following month from a start date

    If I'm understanding correctly, and if your formulas are currently working without issue, then you can just copy the formula you have in B2 in the formula in B3 where you reference B2. Like:
    =WORKDAY((EOMONTH(B1,0)+1),15,G2:G21)

+ Reply to Thread

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Similar Threads

  1. [SOLVED] INPUT month and OUTPUT > Weeks in the month, Start date of Wk & Start date of Wk
    By RavindraK in forum Excel Programming / VBA / Macros
    Replies: 8
    Last Post: 09-06-2018, 10:56 PM
  2. [SOLVED] Calculating Workdays for each quarter from a start and end date
    By ebe in forum Excel Formulas & Functions
    Replies: 5
    Last Post: 06-09-2015, 01:00 PM
  3. Workdays Including Start Date and Saturdays
    By amoto in forum Excel General
    Replies: 2
    Last Post: 05-09-2013, 02:10 PM
  4. Schedule - Start Date and End Date with Unequal Workdays
    By High_Road in forum Excel Formulas & Functions
    Replies: 4
    Last Post: 01-10-2013, 09:48 AM
  5. count number of workdays from a start date
    By asmith in forum Excel Formulas & Functions
    Replies: 3
    Last Post: 10-05-2012, 01:12 PM
  6. Calendar days from start date and workdays
    By mcinnes01 in forum Excel Programming / VBA / Macros
    Replies: 3
    Last Post: 12-17-2010, 10:04 AM
  7. Replies: 8
    Last Post: 03-29-2010, 09:20 PM

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts

Search Engine Friendly URLs by vBSEO 3.6.0 RC 1