Hi Everyone.
I am trying to solve task start and end dates and times based on the following criteria:
- Day Start Time: 09:00
- Day End Time: 17:00
- Break Duration: 1 hour
- Date of first task to be determined by a target completion date of all tasks. E.g. if all tasks should be completed by 16/12/2019 and there are 100 hours worth of work to do, what date would the first task need to start?
- Start time of first task should be 09:00.
- Tasks must only be done on weekdays.
- Start Date of preceding tasks should link to the end date of the predecessor AND if the predecessor task completes within 1 hour of the end of the working day, the next task should start at 09:00 the next day.
Sample data of what I would expect:
Calc. Planned Start Calc. Planned End Hours
08/11/2019 09:00 11/11/2019 16:00 14
12/11/2019 09:00 12/11/2019 17:00 7
13/11/2019 09:00 13/11/2019 15:00 5
13/11/2019 15:00 13/11/2019 17:00 2
14/11/2019 09:00 18/11/2019 10:00 15
Any help is most appreciated.