    Question Gantt Chart without Saturdays and sundays

    Hello everyone ! I took one of the new excel amazing gantt chart template and have been modifying it to suit our needs. There is two problems I can't seem to resolve.


    First : My dates and days go through saturdays and sundays, and I would like for them to not show up, I tinkered with WORKDAYS but I didn't manage to make it do what I want


    Second : You'll see I have a project start date and how many days, and then I assign 1 of my 3 teams to the project. Sometimes, I'll assign 2 teams at once, and the color does change to show 2 teams, but I also need the planned days band to be reduced by the number of days both teams are working together (If I have a 10 day) plan, and I have 1 team work 7 days, and another team work with the first for the first 3 days, then my 10 day plan turns into a 7 days plan)


    Ill upload my excel file
    Attached Files Attached Files

  2. #2
    Forum Moderator - RIP Richard Buttrey's Avatar
    Join Date
    01-14-2008
    Location
    Stockton Heath, Cheshire, UK
    MS-Off Ver
    Office 365, Excel for Windows 2010 & Excel for Mac
    Posts
    29,464

    Re: Gantt Chart without Saturdays and sundays

    Hi, and welcome to the forum

    Change M5 to
    Formula: copy to clipboard
    Please Login or Register  to view this content.


    N5 copied across
    Formula: copy to clipboard
    Please Login or Register  to view this content.
    Richard Buttrey

    RIP - d. 06/10/2022

    If any of the responses have helped then please consider rating them by clicking the small star icon below the post.

  3. #3
    Registered User
    Join Date
    03-06-2020
    Location
    canada
    MS-Off Ver
    365
    Posts
    7

    Re: Gantt Chart without Saturdays and sundays

    Attachment 666164


    It almost worked ! but now it skips fridays and saturdays

  4. #4
    Forum Moderator - RIP Richard Buttrey's Avatar
    Join Date
    01-14-2008
    Location
    Stockton Heath, Cheshire, UK
    MS-Off Ver
    Office 365, Excel for Windows 2010 & Excel for Mac
    Posts
    29,464

    Re: Gantt Chart without Saturdays and sundays

    In N5 change the >=5 to >=6

  5. #5
    Registered User
    Join Date
    03-06-2020
    Location
    canada
    MS-Off Ver
    365
    Posts
    7

    Re: Gantt Chart without Saturdays and sundays

    Awesome perfect ! I'll need to change all my formulas now because all my times that go through the weekends are now 2 days too short. But at least it works

  6. #6
    Registered User
    Join Date
    03-06-2020
    Location
    canada
    MS-Off Ver
    365
    Posts
    7

    Re: Gantt Chart without Saturdays and sundays

    do you have any idea how I could modify my conditional formatting to skip the weekends ? because on my first line now it's supposed to go 10 days but it only goes 8 days since it counts the weekend even if its not there
    Attached Files Attached Files

  7. #7
    Forum Moderator - RIP Richard Buttrey's Avatar
    Join Date
    01-14-2008
    Location
    Stockton Heath, Cheshire, UK
    MS-Off Ver
    Office 365, Excel for Windows 2010 & Excel for Mac
    Posts
    29,464

    Re: Gantt Chart without Saturdays and sundays

    The general cond. format in M9 is

    Formula: copy to clipboard
    Please Login or Register  to view this content.


    applied to $M$9:$CW$19

    For the individual colours add a 3rd element to the AND(). e.g.
    Formula: copy to clipboard
    Please Login or Register  to view this content.

  8. #8
    Registered User
    Join Date
    03-06-2020
    Location
    canada
    MS-Off Ver
    365
    Posts
    7

    Re: Gantt Chart without Saturdays and sundays

    Awesome ! I changed the formulas a little, all my project bands now work flawlessly, skipping the weekends and showing the full
    amount of days ! I changed the formulas a little, I have to add a roundup in there, since we're trying to convert money for the project
    into a number of days, and that number tends to change.

    I'm linking back the up to date excel sheet for the second part of my question. In the example, we have ALAIN working 5 days in blue
    Dominique Working 2 days in red (red + blue = purple) and Eric working 3 days. when I have two teams working together, they obviously work twice
    as fast. I would like the Project chart to shorten with the amount of days 2 teams are working together. In this case, Chalifoux's
    projet pink line should be shortened by 2 days


    If anyone has any idea, I'll gladly take the help
    Attached Files Attached Files

+ Reply to Thread

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Similar Threads

  1. IF Statements, Weekdays, Saturdays & Sundays
    By mh348 in forum Excel Formulas & Functions
    Replies: 21
    Last Post: 01-30-2020, 01:20 PM
  2. [SOLVED] CF Saturdays Sundays and Holidays
    By Excelski in forum Excel General
    Replies: 6
    Last Post: 11-10-2017, 06:10 PM
  3. [SOLVED] Workdays / Saturdays / Sundays in a Month
    By JcOrlando in forum Excel Formulas & Functions
    Replies: 4
    Last Post: 01-03-2014, 12:59 AM
  4. Include Saturdays and maybe Sundays?
    By lil_ern63 in forum Excel Formulas & Functions
    Replies: 12
    Last Post: 06-12-2008, 11:38 AM
  5. counting days excluding saturdays and sundays
    By p_dhoke in forum Excel General
    Replies: 2
    Last Post: 04-24-2007, 04:34 AM
  6. [SOLVED] Calculate the number of Saturdays or Sundays between 2 dates?
    By Jim Long in forum Excel General
    Replies: 1
    Last Post: 11-01-2005, 04:09 PM
  7. Subtract Dates excluding Saturdays and Sundays
    By Shirley Munro in forum Excel General
    Replies: 2
    Last Post: 01-14-2005, 06:26 AM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts

Search Engine Friendly URLs by vBSEO 3.6.0 RC 1