Hello, I have:
A1 5/26/2011 10:34:34 AM
B1 6/3/2011 05:57:30 AM
in C1, I need a formula to calculate the number of working days (rounded with two decimals) that elapsed between these two dates/times.
So, in this example I need to exclude:
5/28 = Saturday (weekend)
5/29 = Sunday (weekend)
5/30 = Monday (Memorial Day)
The answer would be somewhere around 4.79 DAYS
How can I acomplish this?
BTW: We honor all regular US holidays (if there is a place to edit these, all the better)