Hey there,
I am wondering if anyone can assist with the below problem.
In Cell A2 I have an instruction date e.g. 16/06/2012, in Cell B2 I have an end date(or the cell is blank if there is no end date), in Cell C3 I have the formula =IF(ISBLANK(B2),NOW()-A2,B2-A2) this calculates the number of days between the start date and end date (and uses todays date if B2 is blank).
I am looking for assistance with a formula for cell D2 that would return the following:
If C2>42 "Missed"
If C2<=42 "On Target"
If B2 is blank always return "In Progress" regardless of the figure in C2
If A2 is blank always return "Not instructed"
I hope this explains whats I am trying to solve in an understandable way, and thank you in advance if you are able to assist.
-Omniflo