Hello all
I have a report I pull from our system that I need to alter so that a due date is calculated based on the date received.
To give you an idea we receive an item, then there is a 13 working day period between the date received and the date the item will be at the site it was returned from.
Is there a simple or perhaps even complicated function that would perform this?
I have a date received column, date logged column and date completed column and was hoping to at a due date column that calculates based on the date received.
Hope this makes sense, please let me know if you need any more information.
Thanks
Rob