So, I have a document control spreadsheet I'm trying to work up. The idea is to assess risk of document completion on time based on start date, due date and current status. I have these fields:
Start Date - date document started
Current Date - current date
Due Date - date document should be complete
Status - document completion status. This is a drop-down list (data validation list from another worksheet) with the following options:
Assigned
Started
Draft Complete; out for Review by PDC
1st Review Complete; Out for Review by AM
Undergoing Revision
Revisions Complete
Completed
Now, what I need is this. In a column labeled "Risk", a formula should be in place that looks at the difference in due/current date AND the current document status to determine risk of not getting it done on time. Example:
If status is anything other than Undergoing Revision, Revisions Complete, or Completed, AND the difference in due/current date is 3 days or less, then the risk is medium. Make sense?
Thanks!
Bookmarks