+ Reply to Thread
Results 1 to 5 of 5

Using Excel Solver for a complicated capacity problem

  1. #1
    Registered User
    Join Date
    11-21-2013
    Location
    Dayton, Ohio
    MS-Off Ver
    Excel 2010
    Posts
    2

    Using Excel Solver for a complicated capacity problem

    Thanks for viewing the post! Just for background information, I have used Solver in the past in school. However, the problems were not that difficult.

    Currently, I am fighting upper management for my value stream production requirements. So far, scheduling has produced a capacity model (simple) showing that we need an additional machine in a cell. Management used a contractor for a time study and the consultant also stated we needed an additional machine. Still not convinced, management has asked for additional proof, using a Lean tool called a work combination table. The tool breaks down the part into smaller functions consisting of hands on work, automated tasks and walking.

    Here is the problem:
    One operator per shift
    Four machines
    Six Parts that have differing requirements between the operator and machine involving 13 steps
    Each step might involve time for hand, automated and walking times.
    The schedule is rigid for the week.

    Example, for the week, there are different shipping requirements for each part:
    Part A: 55
    Part B: 6
    Part C: 40
    Part D: 15
    Part E: 15
    Part F: 2

    I have seen several examples of minimizing the time to build a part through multiple machines, but the conflict in this is the operator. The operator can only do one operation at a time, so parts are started at different times and come off the machines at different times. I think we can meet the demand by adding an operator per shift and I started trying to use solver, but I am not sure how to set it up. Ultimately, I need to know how many days it takes to meet the schedule.

    Should I give up and do this by hand using a cascading schedule chart typical production is about 100 parts per week. The issue there is knowing how to optmimize between the parts, I can't assume we should run all part A to start. It would be a mixture per machine per day.

    Any input would help!

  2. #2
    Forum Expert Alf's Avatar
    Join Date
    03-13-2004
    Location
    Gothenburg/Mullsjoe, Sweden
    MS-Off Ver
    Excel 2019 and not sure I like it
    Posts
    4,758

    Re: Using Excel Solver for a complicated capacity problem

    so parts are started at different times and come off the machines at different times.
    As solver has no concept of time i.e. all things happened at the same instant this could be difficult to model.

    The operator can only do one operation at a time
    This can easily be modeled using a binary grid.

    At the moment I’m able to imagine how complex you model have to be to take in account all the constraint you need to set up. It could be that the “normal” excel solver is not powerful enough for a task like this.

    Perhaps you could contact the makers of solver and ask for their advice.

    http://www.solver.com/

    Alf
    Attached Files Attached Files

  3. #3
    Forum Expert shg's Avatar
    Join Date
    06-20-2007
    Location
    The Great State of Texas
    MS-Off Ver
    2003, 2010
    Posts
    40,678

    Re: Using Excel Solver for a complicated capacity problem

    Are these machines identical?

    If so, it seems like the problem is to optimize machine operating time. A machine is necessarily idle when the operator is performing setup, but you want to avoid the case where another machine is idle at the same time.
    Entia non sunt multiplicanda sine necessitate

  4. #4
    Forum Expert shg's Avatar
    Join Date
    06-20-2007
    Location
    The Great State of Texas
    MS-Off Ver
    2003, 2010
    Posts
    40,678

    Re: Using Excel Solver for a complicated capacity problem

    As an alternative to pure optimization, you could (one could) write an algorithm that does a relatively simple look-ahead as each machine becomes available, choosing, say, the next six or eight pieces to load that result in the least overlapping down time. That's keeps the number of evaluations down to a million or so at each step, which would be very fast.

    You could run that simulation for your current four machines, then five machines, and see how throughput compares.

  5. #5
    Registered User
    Join Date
    11-21-2013
    Location
    Dayton, Ohio
    MS-Off Ver
    Excel 2010
    Posts
    2

    Re: Using Excel Solver for a complicated capacity problem

    Thanks for your input. I think it is pretty difficult because of the dynamics between the operator tasks and the machine tasks being interdependent. I will contact Solver for advice.

+ Reply to Thread

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Similar Threads

  1. Solver problem/help in excel 2007
    By djgianini in forum Excel General
    Replies: 1
    Last Post: 11-13-2013, 07:37 AM
  2. [SOLVED] Excel Solver Problem - I've never used it
    By mrr2 in forum Excel General
    Replies: 13
    Last Post: 04-08-2013, 03:44 PM
  3. Excel 2007 Complicated Auto-sort/Formatting Problem
    By Rossington in forum Excel Programming / VBA / Macros
    Replies: 1
    Last Post: 09-04-2011, 12:43 PM
  4. Replies: 3
    Last Post: 10-27-2006, 05:53 AM
  5. Interesting Solver problem (Solver encounters an error)
    By MrShorty in forum Excel General
    Replies: 3
    Last Post: 12-22-2005, 06:55 PM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts

Search Engine Friendly URLs by vBSEO 3.6.0 RC 1