Stop Counting Networkdays when a completion date is entered

  1. #1
    Registered User
    Join Date
    05-05-2015
    Location
    USA
    MS-Off Ver
    2013
    Posts
    3

    Stop Counting Networkdays when a completion date is entered

    C3= Start Date
    D3= End Date
    E3= NETWORKDAYS(C3,D3,M2:M14) where range m2:m14 are holidays
    F3=NETWORKDAYS(TODAY(),D3,M2:M14)
    G3=Date Completed

    How do I stop F3 from counting down after G3 is entered. Please help I want to be done with this file already. TIA.
    Attached Files Attached Files

  2. #2
    Forum Moderator - RIP Richard Buttrey's Avatar
    Join Date
    01-14-2008
    Location
    Stockton Heath, Cheshire, UK
    MS-Off Ver
    Office 365, Excel for Windows 2010 & Excel for Mac
    Posts
    29,464

    Re: Stop Counting Networkdays when a completion date is entered

    Hi and welcome to the forum

    One way

    Formula: copy to clipboard
    Please Login or Register  to view this content.
    Richard Buttrey

    RIP - d. 06/10/2022

    If any of the responses have helped then please consider rating them by clicking the small star icon below the post.

  3. #3
    Forum Expert Ace_XL's Avatar
    Join Date
    06-04-2012
    Location
    UAE
    MS-Off Ver
    2016
    Posts
    6,074

    Re: Stop Counting Networkdays when a completion date is entered

    Use

    =NETWORKDAYS(MIN(TODAY(),G3),D3,$M$2:$M$14)
    Life's a spreadsheet, Excel!
    Say thanks, Click *

  4. #4
    Registered User
    Join Date
    05-05-2015
    Location
    USA
    MS-Off Ver
    2013
    Posts
    3

    Re: Stop Counting Networkdays when a completion date is entered

    Do I enter this in F3?...nEVERMIND I got it!
    Last edited by veemarie; 05-05-2015 at 01:42 PM. Reason: resolved my own question

  5. #5
    Forum Guru samba_ravi's Avatar
    Join Date
    07-26-2011
    Location
    Hyderabad, India
    MS-Off Ver
    Excel 2021
    Posts
    8,914

    Re: Stop Counting Networkdays when a completion date is entered

    f3=NETWORKDAYS(MIN(G3,TODAY()),D3,M$2:M$14)
    try this and copy towards down
    Samba

    Say thanks to those who have helped you by clicking Add Reputation star.

  6. #6
    Registered User
    Join Date
    05-05-2015
    Location
    USA
    MS-Off Ver
    2013
    Posts
    3

    Re: Stop Counting Networkdays when a completion date is entered

    Quote Originally Posted by nflsales View Post
    f3=NETWORKDAYS(MIN(G3,TODAY()),D3,M$2:M$14)
    try this and copy towards down
    What do the $ signs do?

  7. #7
    Forum Guru samba_ravi's Avatar
    Join Date
    07-26-2011
    Location
    Hyderabad, India
    MS-Off Ver
    Excel 2021
    Posts
    8,914

    Re: Stop Counting Networkdays when a completion date is entered

    While copying/dragging formula towards down "M$2:M$14" will remain same.

+ Reply to Thread

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Similar Threads

  1. NetWorkDays without counting first date
    By Babs827 in forum Excel General
    Replies: 7
    Last Post: 01-06-2019, 08:10 PM
  2. [SOLVED] Stop Counting Function with NETWORKDAYS plus Conditional Formatting?
    By cmkarnes in forum Excel Formulas & Functions
    Replies: 3
    Last Post: 01-20-2015, 10:29 AM
  3. [SOLVED] Stop age when closed date entered
    By summer2010 in forum Excel General
    Replies: 5
    Last Post: 10-11-2012, 03:16 AM
  4. Replies: 1
    Last Post: 06-08-2011, 02:00 AM
  5. IF function yet want to stop counting when another cell has data entered.
    By Stevie-B in forum Excel Formulas & Functions
    Replies: 2
    Last Post: 04-04-2008, 09:28 AM

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts

Search Engine Friendly URLs by vBSEO 3.6.0 RC 1