Calculate percentage of work complete in hours

  1. #1
    Registered User
    Join Date
    02-09-2011
    Location
    Canada
    MS-Off Ver
    Excel 2007
    Posts
    87

    Calculate percentage of work complete in hours

    How can I get the result to give me % of work complete, and once the remaining hours are Zero, how can the Work complete = 100%


    Cell C3 = 4 hrs
    Cell D3 = 1 hrs
    Cell E3 = %work complete ?

    Attached is my sample sheet
    Attached Files Attached Files
    Oceans Blue

  2. #2
    Forum Guru MarvinP's Avatar
    Join Date
    07-23-2010
    Location
    Woodinville, WA
    MS-Off Ver
    Office 365
    Posts
    16,168

    Re: Calculate percentage of work complete in hours

    Hi Ocean Blue,

    See if the attached gives what you want. If more hours are worked after 100% complete, what do you want it to do?
    Attached Files Attached Files
    One test is worth a thousand opinions.
    Click the * Add Reputation below to say thanks.

  3. #3
    Registered User
    Join Date
    02-09-2011
    Location
    Canada
    MS-Off Ver
    Excel 2007
    Posts
    87

    Re: Calculate percentage of work complete in hours

    Quote Originally Posted by MarvinP View Post
    Hi Ocean Blue,

    See if the attached gives what you want. If more hours are worked after 100% complete, what do you want it to do?
    This is good, but it calculates based on the hours in Cell D2
    every task is independent horizontally
    So i need it to calculate C3 D3 and E3 will give the result of line 3
    Not too sure if this is possible

  4. #4
    Forum Expert newdoverman's Avatar
    Join Date
    02-07-2013
    Location
    Port Dover, Ontario, Canada
    MS-Off Ver
    2010
    Posts
    10,330

    Re: Calculate percentage of work complete in hours

    Maybe this is what you are looking for:
    Enter in E2 format as % and fill down:
    Formula: copy to clipboard
    Please Login or Register  to view this content.


    A
    B
    C
    D
    E
    1
    Start
    Finish
    Work
    Remaining Work
    % Work Complete
    2
    01/09/2015
    06/10/2015
    56 hrs
    56 hrs
    0.00%
    3
    04/09/2015
    02/09/2015
    4 hrs
    1 hrs
    75.00%
    4
    04/09/2015
    04/09/2015
    4 hrs
    1 hrs
    75.00%
    5
    04/09/2015
    07/09/2015
    4 hrs
    1 hrs
    75.00%
    6
    04/09/2015
    07/09/2015
    4 hrs
    1 hrs
    75.00%
    7
    22/09/2015
    25/09/2015
    16 hrs
    7 hrs
    56.25%
    8
    01/10/2015
    02/10/2015
    8 hrs
    6 hrs
    25.00%
    9
    02/10/2015
    05/10/2015
    8 hrs
    6 hrs
    25.00%
    10
    05/10/2015
    06/10/2015
    8 hrs
    6 hrs
    25.00%
    <---------If you like someone's answer, click the star to the left of one of their posts to give them a reputation point for that answer.
    Ron W

  5. #5
    Registered User
    Join Date
    02-09-2011
    Location
    Canada
    MS-Off Ver
    Excel 2007
    Posts
    87

    Re: Calculate percentage of work complete in hours

    Quote Originally Posted by newdoverman View Post
    Maybe this is what you are looking for:
    Enter in E2 format as % and fill down:
    Formula: copy to clipboard
    Please Login or Register  to view this content.


    A
    B
    C
    D
    E
    1
    Start
    Finish
    Work
    Remaining Work
    % Work Complete
    2
    01/09/2015
    06/10/2015
    56 hrs
    56 hrs
    0.00%
    3
    04/09/2015
    02/09/2015
    4 hrs
    1 hrs
    75.00%
    4
    04/09/2015
    04/09/2015
    4 hrs
    1 hrs
    75.00%
    5
    04/09/2015
    07/09/2015
    4 hrs
    1 hrs
    75.00%
    6
    04/09/2015
    07/09/2015
    4 hrs
    1 hrs
    75.00%
    7
    22/09/2015
    25/09/2015
    16 hrs
    7 hrs
    56.25%
    8
    01/10/2015
    02/10/2015
    8 hrs
    6 hrs
    25.00%
    9
    02/10/2015
    05/10/2015
    8 hrs
    6 hrs
    25.00%
    10
    05/10/2015
    06/10/2015
    8 hrs
    6 hrs
    25.00%
    Yes.............
    Thank you!

  6. #6
    Forum Expert newdoverman's Avatar
    Join Date
    02-07-2013
    Location
    Port Dover, Ontario, Canada
    MS-Off Ver
    2010
    Posts
    10,330

    Re: Calculate percentage of work complete in hours

    Thank you for the feedback.

    If that takes care of your original question, please select Thread Tools from the menu link above and mark this thread as SOLVED. Thanks.

+ Reply to Thread

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Similar Threads

  1. Replies: 2
    Last Post: 03-02-2013, 10:57 AM
  2. Calculate / Forecast Estimated Hours to Complete
    By mycon73 in forum Excel General
    Replies: 10
    Last Post: 11-09-2012, 08:17 AM
  3. Replies: 5
    Last Post: 10-18-2010, 08:53 AM
  4. Replies: 4
    Last Post: 09-08-2010, 11:17 AM
  5. Replies: 5
    Last Post: 06-24-2010, 06:21 AM
  6. Replies: 2
    Last Post: 11-27-2008, 11:56 AM

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts

Search Engine Friendly URLs by vBSEO 3.6.0 RC 1