date (minus) date = working days diff

  1. #1
    Registered User
    Join Date
    03-22-2004
    Posts
    14

    Smile date (minus) date = working days diff

    Hello All,

    Quick and easy one (I hope), i have two dates how can i work out the working days between them ?


    Kind Regards
    JJJ

  2. #2
    Niek Otten
    Guest

    Re: date (minus) date = working days diff

    Use the NETWORKDAYS() function
    If you get a #NAME error: Tools>Add-ins, check Analysis Toolpak

    --
    Kind regards,

    Niek Otten

    "jjj" <[email protected]> wrote in message
    news:[email protected]...
    >
    > Hello All,
    >
    > Quick and easy one (I hope), i have two dates how can i work out the
    > working days between them ?
    >
    >
    > Kind Regards
    > JJJ
    >
    >
    > --
    > jjj
    > ------------------------------------------------------------------------
    > jjj's Profile:
    > http://www.excelforum.com/member.php...fo&userid=7424
    > View this thread: http://www.excelforum.com/showthread...hreadid=490742
    >




  3. #3
    Roger Govier
    Guest

    Re: date (minus) date = working days diff

    Hi

    Try =NETWORKDAYS(firstdate,seconddate,holidays)

    Networkdays is part on the Analysis Toolpak so go to Tools>Addins> and
    ensure Analysis Toolpak is selected.

    Substitute the cell reference holding your earliest date for firstdate, and
    the cell ref for your latest date fro seconddate.
    Holidays is either a list of cells containing public holidays, or a named
    range containing the holiday dates.

    Regards

    Roger Govier


    jjj wrote:
    > Hello All,
    >
    > Quick and easy one (I hope), i have two dates how can i work out the
    > working days between them ?
    >
    >
    > Kind Regards
    > JJJ
    >
    >


  4. #4
    JE McGimpsey
    Guest

    Re: date (minus) date = working days diff

    Check out the NETWORKDAYS() function in XL Help. Note that it's an
    Analysis Toolpak Add-in function (Tools/Add-ins...)

    In article <[email protected]>,
    jjj <[email protected]> wrote:

    > Hello All,
    >
    > Quick and easy one (I hope), i have two dates how can i work out the
    > working days between them ?
    >
    >
    > Kind Regards
    > JJJ


+ Reply to Thread

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts

Search Engine Friendly URLs by vBSEO 3.6.0 RC 1