Working ship dates backwards with Networkdays

  1. #1
    Registered User
    Join Date
    04-08-2009
    Location
    NW IL
    MS-Off Ver
    Excel 2003
    Posts
    31

    Working ship dates backwards with Networkdays

    I have a job tracker program that daddylonglegs helped me with a few days ago. I thought I would be able figure this out on my own but failed. I've attached the file to help show what I need. I know the final ship date of a project. Sometimes my projects need to go out for teflon coating. I need Networkdays to give me a TO TEFLON date that is 5 days before the final ship date and factor in weekends and holidays. Thanks in advance.
    Attached Files Attached Files
    Last edited by gibbsmachine; 05-06-2009 at 07:34 AM.

  2. #2
    Forum Expert daddylonglegs's Avatar
    Join Date
    01-14-2006
    Location
    England
    MS-Off Ver
    2016
    Posts
    14,675

    Re: Working ship dates backwards with Networkdays

    If you want to add (or subtract) a number of working days to a date then, rather than NETWORKDAYS you can use WORKDAY function, so in F3 try this formula copied down

    =IF(D3="Yes",WORKDAY(G3,-A$14,A$17:A$29),"")

  3. #3
    Registered User
    Join Date
    04-08-2009
    Location
    NW IL
    MS-Off Ver
    Excel 2003
    Posts
    31

    Re: Working ship dates backwards with Networkdays

    Thanks again, that worked great.

+ Reply to Thread

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts

Search Engine Friendly URLs by vBSEO 3.6.0 RC 1