Hi all,
Having trouble with a graph that I thought would be easy..
Please attachment. basically, I need to show a graph for the current dates and the associated values for those dates. that's easy enough but I also need to show what the dates and the associated values were when we took a baseline. It's easy to show the change in values but when the dates have changed from the baseline also, I cant seem to show this as the x axis being the dates can only be the current or baseline dates!!?? I was thinkign of somehow overlaying the graphs, both with different x axis dates but couldnt work out how to do this. Any one any workarounds for this?
Any help is greatly appreciated.
Anthony.