I have a Formula that someone else had built that is very simple, the start date is entered manually and then it calculates when each step of the process should be complete based on another cell that has time each process takes.
So for example
A1 = 3/4/2013 (manually entered) B1 = A1+B2 (B2 would have the amount of time for a process) and this goes on for 12 cells. The problem is that it does not exclude weekends/holidays. Is there a way to do this? I already have a table of off-days (weekends, off fridays, and Holidays.)