Dear Friends,
Please find my attached Excel File Where
Column A Contains “Product Code”
Column B Contains “Segment”
Column C Contains “Qty which needs to separated”
Column D contains “Std. Hours”
Column E contains “Max Output” Qty to be separated per day in align with this qty
Column F contains “Start Date” Qty To be separated from this particular date only
Column K onwards sequential dates are updated
Row No. 2 Contains “Each Day Wise what is the available Man Power”
Row No. 3 contains “Formula which will auto populate loaded HC” based on qty which is getting separated on each Day
Support Required: -
Each Product, Column C mentioned qty should be separated by validating following criteria in sequence
Criteria 1 - Qty To be separated must be >0
Criteria 2 – Qty separation to be started from start date onwards subjected to 2 layer validation. Validation 1 Available Man Power is > Loaded Manpower, Validation 2 After aligning the qty Loaded Man Power should be<=Available Man Power
Criteria 3 :- If Start date is already met with above criteria; excel should look for next available date where criteria 2 Meets and separate the qty
In Summary All “Qty To Be Separated” value separated into each date based on above criteria’s
Your suggestion can be in the form of Formula or VBA too Fine!
Thanks & Regards,
Rajeshkumar R