Hi All,
I have been trying to create a high-level project plan that shows the duration of tasks(horizontally) and the date per month on tasks on the x axis
The trouble I am having is that on my x axis I cannot seem to get the axis to be date based and I am really struggling to see why. It would be great if I could do this as then I would be able to achieve consistent monthly dates across the bottom i.e 1st Nov, 1st Dec, 1st Jan etc
Start Duration
"Requirements Gathering" 10 November 2014 18
"Test Environment Creation" 10 November 2014 11
"Data Cleanse" 01 December 2014 11
Test System Configuration 12 December 2014 35
I have literally searched everywhere for an answer to no avail, and my date column is in date format