I'm having trouble figuring out how to graph $ Volume over time and was hoping someone on here could help me out.
This is an example of the data I have:
PM Name Pro. Name Project Cost Start Date End Date Duration $/Day
Andrew X. Project A $850,000 1/23/2015 6/1/2015 129 $6,589.15
Andrew X. Project B $123,400 3/1/2015 4/10/2015 40 $3,085.00
Andrew X. Project C $650,000 4/15/2015 6/15/2015 61 $10,655.74
Andrew X. Project D $75,000 5/1/2015 5/15/2015 14 $5,357.14
Andrew X. Project E $2,239,900 5/1/2015 10/1/2015 153 $14,639.87
I'm trying to graph a sum of the project manager's $ Volume over time in that for an X value of 1/23/2015, the Y value would be $6,589 and then at X value 3/1/2015, the Y value would be $6,589 + $3085. I am stuck at trying to determine how to have the X value be a date range and have the Y values add.
Any help would be greatly appreciated.
Thanks,
Brendan