In a GANTT, how do I get diff projects to start later on chart

  1. #1
    Tim
    Guest

    In a GANTT, how do I get diff projects to start later on chart

    I want to show a flow of projects, by date. When one stops, the other starts
    or maybe the next starts a couple days before. How do you set up the GANTT
    to show the stepping effect. Currently all I can get it to do is all
    projects start at the same time. Thanks for the help

  2. #2
    Jon Peltier
    Guest

    Re: In a GANTT, how do I get diff projects to start later on chart

    A project bar in a Gantt chart is the stacked bar defined by a start date and a
    duration. To make a bar start later, give it a later start date. You should be able
    to use formulas to relate a later start to the earlier starting date and duration of
    another bar.

    These articles might be of assistance:

    http://pubs.logicalexpressions.com/P...cle.asp?ID=343
    http://peltiertech.com/Excel/Charts/GanttChart.html

    - Jon
    -------
    Jon Peltier, Microsoft Excel MVP
    Peltier Technical Services
    Tutorials and Custom Solutions
    http://PeltierTech.com/
    _______

    Tim wrote:

    > I want to show a flow of projects, by date. When one stops, the other starts
    > or maybe the next starts a couple days before. How do you set up the GANTT
    > to show the stepping effect. Currently all I can get it to do is all
    > projects start at the same time. Thanks for the help



+ Reply to Thread

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts

Search Engine Friendly URLs by vBSEO 3.6.0 RC 1