I have made a Timeline chart (gnatt chart). How to show half days in it? Say, first gnatt ends at 1.5 days. Next gnatts start from where last gnatt ended. I have attached the chart. Request guidance.
Hello!
I have made a Timeline chart (gnatt chart). How to show half days in it? Say, first gnatt ends at 1.5 days. Next gnatts start from where last gnatt ended. I have attached the chart. Request guidance.
Change your chart X axis to a minor unit of .5 that will allow the showing of your 1/2 days
Hi optomyst,
Thanks for your response. What you said that was possible for first gnatt even without changing the x axis minor unit to 0.5 but what about 2nd or 3rd gnatts they are required to start from where the last gnatt ends. For example, 2nd gnatt is for 3 days and it has to start from 1/2 day of 22/11/2011 i.e. where the 1st gnatt has ended. Hope I could make it clear now. Thanks again.