Hi,
I've been stuck on this problem longer than I expected and am reaching out for help.
I am working on a project planning spreadsheet where I am inputting planned effort in work days, and a start date, and I want to calculate the end date. The tricky part is that I am only inputting work days, and not weekends. I am also using a work week format to express the dates, so Tuesday July 1, 2014 would be expressed as 27.2 because it is the 27 week of the year and Tuesday is the 2nd day (assuming Monday is the 1st day).
An example of what I expect to achieve is below:
TASK EFFORT (input) START DATE (input) END DATE (output) Task A 3 24.1 24.3 Task B 3 24.5 25.2 Task C 20 25.3 29.2
Anyone have a suggestion or even better, the universal formula I could use to get the correct result?
Thanks in advance!
Bookmarks