Does anyone have any suggestions for a formula or approach (without any macros) that returns the answers in column F (available to start date) given the data in columns A-E. Additional columns can be added and there would not be more than 10 predecessors to any task.
The "available to start date" for any task is defined as the day following the latest "finish date" of the predecessor tasks where the predecessors have the same project number.
So for task 26 of project Beta the predecessors are tasks 8A and 9A. 9A has the latest finish date of 1/14/16 so the "available to start date" of Task 26 is one day later or 1/15/16
If a task has no predecessor the available to start date should be either blank or zero.
Here's a screenshot of the data and it is also attached as xlsx
Any help would be greatly appreciated
Capture.PNG
Bookmarks