+ Reply to Thread
Results 1 to 4 of 4

Date calculation with Networkdays & holidays - formula is slightly off

  1. #1
    Registered User
    Join Date
    05-02-2016
    Location
    New Zealand
    MS-Off Ver
    Microsoft Excel 2010
    Posts
    21

    Question Date calculation with Networkdays & holidays - formula is slightly off

    Hi all,

    Please see attached sample workbook where my formula for calculating the removal of public holidays appears to be slightly off. Minutes and seconds seem to be calculated fine, but days aren't. Not sure where I've gone wrong! Any help appreciated

    Cheers!
    Attached Files Attached Files

  2. #2
    Forum Guru samba_ravi's Avatar
    Join Date
    07-26-2011
    Location
    Hyderabad, India
    MS-Off Ver
    Excel 2021
    Posts
    8,914

    Re: Date calculation with Networkdays & holidays - formula is slightly off

    is there any chance the expected date of delivery may be on weekends or national holidays or it will be purely on working day
    Samba

    Say thanks to those who have helped you by clicking Add Reputation star.

  3. #3
    Forum Guru samba_ravi's Avatar
    Join Date
    07-26-2011
    Location
    Hyderabad, India
    MS-Off Ver
    Excel 2021
    Posts
    8,914

    Re: Date calculation with Networkdays & holidays - formula is slightly off

    what is your expected result in that cases and why can you explain
    your expected date fall under public holiday then how to treat that day

  4. #4
    Registered User
    Join Date
    05-02-2016
    Location
    New Zealand
    MS-Off Ver
    Microsoft Excel 2010
    Posts
    21

    Re: Date calculation with Networkdays & holidays - formula is slightly off

    Hi nflsales,

    Sorry should have made that clearer! I was expecting the formula to take both weekends and the public holidays into account that
    I've added to the Networkdays formula (in the Lookups worksheet). On further review, I can see that it actually has (I've gotten confused)! The formula works perfectly...
    The "How many days difference?" column is showing how many WORKING DAYS difference, rather than how many actual days difference. Based on that, the formula is actually working
    as it should be.

+ Reply to Thread

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Similar Threads

  1. NETWORKDAYS for current week minus holidays no start date
    By blackburnsexcel in forum Excel General
    Replies: 2
    Last Post: 08-24-2015, 10:08 AM
  2. Replies: 6
    Last Post: 05-20-2013, 07:45 PM
  3. Date and time calculation - networkdays, vacation, holidays
    By N8237 in forum Excel Programming / VBA / Macros
    Replies: 0
    Last Post: 03-21-2013, 10:47 AM
  4. Replies: 6
    Last Post: 09-04-2012, 09:29 AM
  5. [Formula] NETWORKDAYS with fixed holidays?
    By stewegg in forum Excel General
    Replies: 0
    Last Post: 02-09-2011, 03:18 PM
  6. Replies: 2
    Last Post: 09-13-2010, 04:53 AM
  7. Slightly complex conversion and date calculation
    By Junior19 in forum Excel General
    Replies: 4
    Last Post: 05-07-2008, 07:16 AM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts

Search Engine Friendly URLs by vBSEO 3.6.0 RC 1