Formula incorrect to automate gantt based on start date and task duration

  1. #1
    Forum Contributor
    Join Date
    07-22-2015
    Location
    San Francisco
    MS-Off Ver
    Mac 2011 Version 14.5.2
    Posts
    107

    Formula incorrect to automate gantt based on start date and task duration

    Hello,

    I have a gantt chart where I want the gantt to automate through conditional formatting (see attached excel). I believe the conditional formatting is correct, but the current formula is incorrect that generates true or false based off the month and task duration.

    Note, I have manually shaded the excel to show what I want it to look like.

    Any help to update the formula would be much appreciated.

    Many thanks,
    A
    Attached Files Attached Files

  2. #2
    Valued Forum Contributor
    Join Date
    01-10-2012
    Location
    Texas
    MS-Off Ver
    Excel 2010
    Posts
    651

    Re: Formula incorrect to automate gantt based on start date and task duration

    try this in k4 and fill all the way right and down:
    Formula: copy to clipboard
    Please Login or Register  to view this content.

    for your conditional formatting, try a using a formula to determine which cells to format, and in the formula bar input =k4=true(), applied to the range $k$4:$ah$21

    be careful about the $'s, they're quite important.
    Hope I could help - if your post has been solved don't forget to mark it as such.

    Clicking the * below is a great way to say thanks!

    "Drowning in 10 feet of water isn?t any different than drowning in a million feet. And if you can swim, it doesn?t matter how deep the ocean is. At some level, once you realize you?re in water that?s too deep to stand, you have to have a very different approach," - Joi Ito

  3. #3
    Forum Contributor
    Join Date
    07-22-2015
    Location
    San Francisco
    MS-Off Ver
    Mac 2011 Version 14.5.2
    Posts
    107

    Re: Formula incorrect to automate gantt based on start date and task duration

    Hi Simarui -- that works great. Thanks for helping with that!

+ Reply to Thread

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Similar Threads

  1. Replies: 7
    Last Post: 03-07-2018, 03:10 PM
  2. Replies: 6
    Last Post: 10-04-2016, 05:01 PM
  3. Have start-stop times & duration, need sub-duration based on range criteria
    By CathTyner in forum Excel Formulas & Functions
    Replies: 9
    Last Post: 09-23-2016, 01:53 AM
  4. Plotting a Task(s) on a day(s) w/start time and duration.
    By sorensjp in forum Excel Programming / VBA / Macros
    Replies: 0
    Last Post: 09-04-2016, 06:50 PM
  5. [SOLVED] Need formula to calucalte based on start month # and duration # of months
    By NS4Excel in forum Excel Formulas & Functions
    Replies: 3
    Last Post: 03-14-2014, 05:59 PM
  6. Calculating a minutes duration based on start and end date and times
    By chrispx001 in forum Excel Formulas & Functions
    Replies: 4
    Last Post: 03-12-2013, 08:16 AM
  7. Calculate START date based on duration (work hours) and END date
    By kaaver in forum Excel Formulas & Functions
    Replies: 0
    Last Post: 07-06-2010, 12:21 PM

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts

Search Engine Friendly URLs by vBSEO 3.6.0 RC 1