Need syntax/formula for calculating a date when a task reaches 100%

  1. #1
    Registered User
    Join Date
    07-14-2018
    Location
    Liverpool, England
    MS-Off Ver
    2016 Pro
    Posts
    5

    Need syntax/formula for calculating a date when a task reaches 100%

    Re-posted due to both previous threads being closed due to my mistakes in posting a new thread...

    I have a spreadsheet which records progress day by day for a 3 week shutdown project.

    Progress is entered on a daily basis for each individual task as a percentage until that task is complete.

    Some tasks are completed in one day, others may take multiple days and hence have different finish days.


    I also have a column for summarising the %age complete, which simply adds up each cell with the daily percentages entered into them. Of course once a task reaches 100%, either cumulatively or on a single day, the %age column shows 100% and no more progress is entered on the columns for measuring daily progress. Hence the final day of progress input ='s the day on which the task is completed.

    Thus I have many different tasks, c. 2,500 which reach 100% on different days.

    I would like to go back retrospectively and record the day on which each task completed. I could do this by writing a formula to reflect the following

    when sum of progress = 1 in the horizontal series of cells from AA11 (where I have the date of 02/07/2018) to AU11 (where I have the date of 22/07/2018) enter date from cell $1?? where ?? would correspond to the the column reference for the appropriate date

    e.g.

    Project starts on 02/07/2018 and lasts until 22/07/2018.

    Let's say Task 1 starts on 2nd July and finishes on the 11th.

    I enter a series of progress updates say day 1 = 0.1 (=10%), day 2 = 0.2, day 3 = 0.1, day 4 = 0.1, day 5 = .05 day 6 & 7 = weekend = 0.0, day 8 = 0.2, day 9 = 0.2, day 10 = 0.05

    So on day 10 I have achieved 100%. This now means that the sum of the cells AA5 to AJ5 = 1 which ='s 100%, . The date is in row 2 cell ref AJ$2. So I know want to copy that date and enter it into the column recording completion dates which would be say G5.

    I don't have a clue where to start in terms of selecting perhaps a logical statement or writing the correct syntax to achieve this, which surely must be possible?

    My alternative is to go through all 2,500 tasks, identify the point at which progress = 100% and manually enter the appropriate date into G5.

    One way I'm thinking is that if I have a start and finish of a series of inputs, and the finish is recognisable by the point at which the last numerical entry >0 is entered, then if I could write a formula to identify this cell and then capture the date from the cell ref ??$2 this might be possible.

    Any help most appreciated,

    Neal

  2. #2
    Forum Moderator Glenn Kennedy's Avatar
    Join Date
    07-08-2012
    Location
    Digital Nomad... occasionally based in Ireland.
    MS-Off Ver
    O365 (PC) V 2403
    Posts
    44,063

    Re: Need syntax/formula for calculating a date when a task reaches 100%

    Too many words.... can't see what's needed.



    Will you please attach a SMALL sample Excel workbook (10-20 rows of data is usually enough)? Please don't attach a picture of one (no-one will want to re-type all your stuff before starting).

    1. Make sure that your sample data are truly REPRESENTATIVE of your real data. The use of unrepresentative data is very frustrating and can lead to long delays in reaching a solution.

    2. Make sure that your desired solution is also shown (mock up the results manually).

    3. Make sure that all confidential information is removed first!!

    4. Try to avoid using merged cells. They cause lots of problems!

    Unfortunately the attachment icon doesn't work at the moment. So, to attach an Excel file you have to do the following: Just before posting, scroll down to Go Advanced and then scroll down to Manage Attachments. Now follow the instructions at the top of that screen.
    Glenn




    None of us get paid for helping you... we do this for fun. So DON'T FORGET to say "Thank You" to all who have freely given some of their time to help YOU.

    Temporary addition of accented to illustrate ongoing problem to the TT: L? fh?ile P?draig sona dhaoibh

+ Reply to Thread

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Similar Threads

  1. [SOLVED] Calculating time to do a task
    By Journeyman3000 in forum Excel Formulas & Functions
    Replies: 22
    Last Post: 04-08-2022, 02:13 AM
  2. Calculating a task due date incorporating part days
    By JMB73 in forum Excel Formulas & Functions
    Replies: 4
    Last Post: 10-11-2017, 04:05 AM
  3. [SOLVED] Formula to return corresponging date value in row 1 once row 2 payment sum reaches a value
    By wannabeexcelguy in forum Excel Formulas & Functions
    Replies: 6
    Last Post: 02-08-2016, 10:24 AM
  4. [SOLVED] Formula to add date when task is completed
    By rizmomin in forum Excel Formulas & Functions
    Replies: 5
    Last Post: 11-26-2015, 02:17 PM
  5. Replies: 1
    Last Post: 08-17-2015, 05:02 PM
  6. Want function to stop calculating when it reaches a blank cell
    By GrogRogers in forum Excel Formulas & Functions
    Replies: 4
    Last Post: 02-01-2015, 03:49 PM
  7. displaying a date when a row reaches a certain value
    By sfay6304 in forum Excel General
    Replies: 4
    Last Post: 10-20-2014, 06:40 PM

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts

Search Engine Friendly URLs by vBSEO 3.6.0 RC 1