how do I adjust working calendar (6 day work week) in excel that .

  1. #1
    Hatem
    Guest

    how do I adjust working calendar (6 day work week) in excel that .

    I need to use the WORKDAY function, but adjust the working calendar to have
    Friday and Saturday as the weekend, and in another case to work with 6 day
    work weeks. I cannot find anything in excel (as in MS Project) that lets me
    define the working calendar.

  2. #2
    Bob Phillips
    Guest

    Re: how do I adjust working calendar (6 day work week) in excel that .

    That is because Project is designed to work with schedules, Excel isn't. It
    can't do everything (and should certainly not try to).

    Don't have an answer for the first one yet, but I'll keep trying, but the 6
    day week can be solved with this formula that Frank Kabel posted just before
    Christmas

    =A1+IF(A2=0,0,SIGN(A2)*SMALL(IF((WEEKDAY(A1+SIGN(A2)*(ROW(INDIRECT("1:"&ABS(
    A2)*10))),2)<7)*ISNA(MATCH(A1+SIGN(A2)*(ROW(INDIRECT("1:"&ABS(A2)*10))),holi
    days,0)),ROW(INDIRECT("1:"&ABS(A2)*10))),ABS(A2)))

    where A1 is the start date, A2 is the duration, and you must have a range
    called holidays, even if there are no dates in it.

    --

    HTH

    RP
    (remove nothere from the email address if mailing direct)


    "Hatem" <[email protected]> wrote in message
    news:[email protected]...
    > I need to use the WORKDAY function, but adjust the working calendar to

    have
    > Friday and Saturday as the weekend, and in another case to work with 6 day
    > work weeks. I cannot find anything in excel (as in MS Project) that lets

    me
    > define the working calendar.




+ Reply to Thread

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts

Search Engine Friendly URLs by vBSEO 3.6.0 RC 1