workdays formula ends on weekend date

  1. #1
    Charles C.
    Guest

    workdays formula ends on weekend date

    I'm trying to calculate end dates similar to MS Project based upon a start
    date and duration in workdays.

    Start Date = 1/3/2006
    Workdays = 28 - 1 day adjustment to get the END DATE
    Holidays = ignore for now, not using it

    Therefore... formula is WORKDAYS(1/3/2006,28)-1 = 2/9/2006
    this is okay, but when increased to 29 days the end date should be 2/10/2006
    but Excel jumps to 2/12/2006 which is a Sunday.

    Why? What am i doing wrong?


  2. #2
    Biff
    Guest

    Re: workdays formula ends on weekend date

    Hi!

    I don't know why you're subtracting a day, but you need to subtract the day
    inside the function:

    =WORKDAY("1/3/2006",29-1)

    But if you're doing that then why not just:

    =WORKDAY("1/3/2006",28)

    Biff

    "Charles C." <Charles [email protected]> wrote in message
    news:[email protected]...
    > I'm trying to calculate end dates similar to MS Project based upon a start
    > date and duration in workdays.
    >
    > Start Date = 1/3/2006
    > Workdays = 28 - 1 day adjustment to get the END DATE
    > Holidays = ignore for now, not using it
    >
    > Therefore... formula is WORKDAYS(1/3/2006,28)-1 = 2/9/2006
    > this is okay, but when increased to 29 days the end date should be
    > 2/10/2006
    > but Excel jumps to 2/12/2006 which is a Sunday.
    >
    > Why? What am i doing wrong?
    >




  3. #3
    Charles C.
    Guest

    Re: workdays formula ends on weekend date

    Biff

    Subtracting the day becuase workdays is inclusive of the start and end dates.

    Doing it outside of the formula was the problem.
    Thanks.

    "Biff" wrote:

    > Hi!
    >
    > I don't know why you're subtracting a day, but you need to subtract the day
    > inside the function:
    >
    > =WORKDAY("1/3/2006",29-1)
    >
    > But if you're doing that then why not just:
    >
    > =WORKDAY("1/3/2006",28)
    >
    > Biff
    >
    > "Charles C." <Charles [email protected]> wrote in message
    > news:[email protected]...
    > > I'm trying to calculate end dates similar to MS Project based upon a start
    > > date and duration in workdays.
    > >
    > > Start Date = 1/3/2006
    > > Workdays = 28 - 1 day adjustment to get the END DATE
    > > Holidays = ignore for now, not using it
    > >
    > > Therefore... formula is WORKDAYS(1/3/2006,28)-1 = 2/9/2006
    > > this is okay, but when increased to 29 days the end date should be
    > > 2/10/2006
    > > but Excel jumps to 2/12/2006 which is a Sunday.
    > >
    > > Why? What am i doing wrong?
    > >

    >
    >
    >


+ Reply to Thread

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts

Search Engine Friendly URLs by vBSEO 3.6.0 RC 1