Due date excluding weekend days

  1. #1
    Registered User
    Join Date
    02-03-2006
    Posts
    1

    Due date excluding weekend days

    Need formula to add 3, 5 or 20 days to a start date and exlude sat sun.
    Help please

  2. #2
    Niek Otten
    Guest

    Re: Due date excluding weekend days

    Look at the WORKDAY() function, which does just that.
    If you get a #NAME error: Tools>Add-ins, check Analysis Toolpak

    --
    Kind regards,

    Niek Otten

    "Jfilbig" <[email protected]> wrote in
    message news:[email protected]...
    >
    > Need formula to add 3, 5 or 20 days to a start date and exlude sat
    > sun.
    > Help please
    >
    >
    > --
    > Jfilbig
    > ------------------------------------------------------------------------
    > Jfilbig's Profile:
    > http://www.excelforum.com/member.php...o&userid=31156
    > View this thread: http://www.excelforum.com/showthread...hreadid=508185
    >




  3. #3

    Re: Due date excluding weekend days

    Or maybe: Look at NETWORKDAYS () which excludes weekends and andy
    defined holidays.

    Hans


  4. #4
    Ron Rosenfeld
    Guest

    Re: Due date excluding weekend days

    On 3 Feb 2006 10:10:10 -0800, [email protected] wrote:

    >Or maybe: Look at NETWORKDAYS () which excludes weekends and andy
    >defined holidays.
    >
    >Hans


    How do you use NETWORKDAYS to add 10 days to a given date?


    --ron

  5. #5
    Chip Pearson
    Guest

    Re: Due date excluding weekend days

    To add days, use the WORKDAY function.


    "Ron Rosenfeld" <[email protected]> wrote in message
    news:[email protected]...
    > On 3 Feb 2006 10:10:10 -0800, [email protected] wrote:
    >
    >>Or maybe: Look at NETWORKDAYS () which excludes weekends and
    >>andy
    >>defined holidays.
    >>
    >>Hans

    >
    > How do you use NETWORKDAYS to add 10 days to a given date?
    >
    >
    > --ron




  6. #6
    Ron Rosenfeld
    Guest

    Re: Due date excluding weekend days

    On Sun, 5 Feb 2006 09:03:26 -0600, "Chip Pearson" <[email protected]> wrote:

    >To add days, use the WORKDAY function.
    >
    >


    I know that. I was wondering why Hans was recommending the NETWORKDAYS
    function.
    --ron

+ Reply to Thread

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts

Search Engine Friendly URLs by vBSEO 3.6.0 RC 1