Example Problem.xlsxHi Guys and Gals,
Just making my own review program/little project at work and need some tips for some formulas that would make my spreadsheet complete.
I will attach a spreadsheet that will show you what I am rambling on about.
Looking at the Attached Spreadsheet:
1. I have already used the COUNTIF Function to determine how many items from the "Package 1 Details" (Sheet 2) go into which status heading of the "Report" (Sheet 1).
I.e. For Package 1:
Submission (B3) =COUNTIF('Package 1 Details'!B4:B21,"Submittal")
Processing (C3) =COUNTIF('Package 1 Details'!B4:B21,"Processing")
Review (D3) =COUNTIF('Package 1 Details'!B4:B21,"Review")
Review Processing (E3) =COUNTIF('Package 1 Details'!B4:B21,"Review Processing")
Resubmission (F3) =COUNTIF('Package 1 Details'!B4:B21,"Resubmittal")
Completed Items (G3) =COUNTIF('Package 1 Details'!B4:B21,"Complete")
That's the easy part done....
2. What I would like to do now is to go back to the "Package 1 Details" (Sheet 2) and determine how many of the individual status' are overdue, AND by how much. I would like to have Status overdue by 1-7 days, 7-14 days and 14+ days according to the Review Date (H1).
Obviously, I do not need to worry about the Completed Items so that leaves 5 Status'.
(Submission/Processing/Review/Review Processing/Resubmission)
(1-7 Days Overdue/7-14 Days Overdue/14+ Days Overdue)
For example, Submission: 1-7 Days Overdue - I have a feeling it would be something along the lines of:
=COUNTIF('Package 1 Details'!B4:B21,"Submittal")AND(Today(Report!H1)-"'Package 1 Details'!A4:A21"<7))
3. Could you please advise the correct formulas I should use to determine the said days overdue for each specific status?
Kind Regards,
Chalmers