Hello,
I have a spreadsheet with the following dates
Created = 5/9/12 2:26 PM
Assigned = 5/11/2012 4:00 PM
Completed = 7/18/2012 10:30 AM
I wanted to create three formulas: Created to Completed, Created to Assigned, and Assigned to Completed
I started with Created to Completed and came up with:
=(NETWORKDAYS([@Created],[@[Completed Date]],'Do NOT DELETE Time Frames'!N$2:N$12)-1+([@[Completed Date]]-INT([@[Completed Date]]))-([@Created]-INT([@Created])))
Can someone please check it for me? It's coming out to total 16:20:03. The total days:hours:minutes (excluding weekends and holidays) should be more than 30 days. It works for some dates and not for others.
Then for the other two formulas I thought I would just substitute the cells and it would be the same concept.
Please let me know! Thanks!