Hi Everyone,
Assume I have start date of a project (eg: 1-Nov-2012) and looking for a formula to calculate end date. Considering project duration is 100 Days by excluding Fridays & Saturdays and listed holidays.
I have tried Workday formula, but it considering only standard weekends . Highly appreciate your valuable inputs.
Thanks & Regards,
Nawas