Hello! I am needing to add 89 days to an existing date in order to populate an end date. For example:: 3/25/14 +89 days equals what
Hello! I am needing to add 89 days to an existing date in order to populate an end date. For example:: 3/25/14 +89 days equals what
As long as the dates in the cells you're referencing are numeric dates and not text, this works like normal math.
A1: 3/25/15
B1: =A1+89 (format this cell as Date)
BTW, When you joined the forum recently you agreed to abide by the Forum Rules, but in haste I fear you might not have actually read them. Please stop and take a moment to read them now. We all follow these rules for the benefit of all, as must you. Thanks.
(link above in the menu bar)
I've corrected the TITLE on this thread for you as per forum rules as a courtesy.
_________________
Microsoft MVP 2010 - Excel
Visit: Jerry Beaucaire's Excel Files & Macros
If you've been given good help, use the icon below to give reputation feedback, it is appreciated.
Always put your code between code tags. [CODE] your code here [/CODE]
?None of us is as good as all of us? - Ray Kroc
?Actually, I *am* a rocket scientist.? - JB (little ones count!)
There are currently 1 users browsing this thread. (0 members and 1 guests)
Bookmarks