+ Reply to Thread
Results 1 to 8 of 8

Eliminate weekends and holidays from schedule

  1. #1
    Registered User
    Join Date
    09-18-2012
    Location
    Illinois
    MS-Off Ver
    Microsoft 360
    Posts
    58

    Eliminate weekends and holidays from schedule

    Hi All,

    I attached a sample spreadsheet to help explain what I am trying to do. I work in a printing production facility and the customer usually indicates the date the project needs to be completed and when it will ship. We have various departments that perform various functions and each department requires a specific number of days to complete their portion of the project. What we would like to do before the job enters the facility is to ask the customer what date the project needs to ship. We would then enter that date along with the number of days required to complete each function. We would like the spreadsheet to calculate which date each department needs to complete their part of the project based on the number of days each department needs to perform their function. Then, we would be able to know what date the process of receiving the order needs to take place. If we worked 7 days a week and holidays, the calculation would be simple (as in my example). However, we only schedule work 5 days a week and do not work on holidays. Is there a way to run these calculations and omit Saturdays, Sundays and holidays from the calculation? I know the NETWORKDAYS function, but that only tells me how many work days between 2 dates. I need to work backwards from the due date. Any way to do this?

    Thanks, Joe
    Attached Files Attached Files

  2. #2
    Forum Expert newdoverman's Avatar
    Join Date
    02-07-2013
    Location
    Port Dover, Ontario, Canada
    MS-Off Ver
    2010
    Posts
    10,330

    Re: Eliminate weekends and holidays from schedule

    I think that this is what you want. Enter in C2 and fill down. This takes weekends and holidays into consideration.

    Formula: copy to clipboard
    Please Login or Register  to view this content.
    Attached Files Attached Files
    Last edited by newdoverman; 12-04-2014 at 10:37 PM.
    <---------If you like someone's answer, click the star to the left of one of their posts to give them a reputation point for that answer.
    Ron W

  3. #3
    Registered User
    Join Date
    09-18-2012
    Location
    Illinois
    MS-Off Ver
    Microsoft 360
    Posts
    58

    Re: Eliminate weekends and holidays from schedule

    Thanks newdoverman, but I am confused because it doesn't seem to be working for me. I am not sure what you mean should be entered in C2. Is there any way to enter the final date in C17 and have the spreadsheet count backwards to C2 while subtracting the number of days in Column B for each entry? Also, are both columns C and D necessary? Thanks!

  4. #4
    Forum Expert newdoverman's Avatar
    Join Date
    02-07-2013
    Location
    Port Dover, Ontario, Canada
    MS-Off Ver
    2010
    Posts
    10,330

    Re: Eliminate weekends and holidays from schedule

    Going backwards is a little counterintuitive as the weekends and holidays have to be factored in so that the starting date can be determined.

  5. #5
    Registered User
    Join Date
    09-18-2012
    Location
    Illinois
    MS-Off Ver
    Microsoft 360
    Posts
    58

    Re: Eliminate weekends and holidays from schedule

    Perfect ... that is exactly what I needed. Thanks!

  6. #6
    Forum Expert newdoverman's Avatar
    Join Date
    02-07-2013
    Location
    Port Dover, Ontario, Canada
    MS-Off Ver
    2010
    Posts
    10,330

    Re: Eliminate weekends and holidays from schedule

    Thank you for the feedback.

  7. #7
    Registered User
    Join Date
    09-18-2012
    Location
    Illinois
    MS-Off Ver
    Microsoft 360
    Posts
    58

    Re: Eliminate weekends and holidays from schedule

    Newdoverman,

    I need to ask you another question regarding the spreadsheet you assisted me with. I just found out that the version that is going to be available to me is not 2010, but 2007. So, I did some research and modified your formula slightly to WORKDATE STARTDATE and it works with 2007. Now, there is another little issue I need to work on. It seems that there are going to be some constant dates in this spreadsheet ... for example, there will always be 7 days from Activity 1 to Activity 13 and there will always be 6 days from Activity 2 to Activity 13 and there will always be 4 days from Activity 4 to Activity 13. There can be others with the same structure and some in which we can just add the number of days in column B.

    I need to know if there is a formula I can add between any 2 specific Activities that will give me a specified number of days while still observing holidays, Saturdays and Sundays. I hope I explained that correctly and that it makes sense. Thanks!
    Attached Files Attached Files

  8. #8
    Forum Expert newdoverman's Avatar
    Join Date
    02-07-2013
    Location
    Port Dover, Ontario, Canada
    MS-Off Ver
    2010
    Posts
    10,330

    Re: Eliminate weekends and holidays from schedule

    I have changed the formula a bit for activity 2, 4 and 13 to take into consideration the number of working days between these activities. This means that the other activities will likely have completion dates that are before and after the fixed dates (out of order). Changing column B will change the starting date for all activities. I think that you should test this out before actually putting it into practice for real.

+ Reply to Thread

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Similar Threads

  1. Statement to search date range and eliminate weekends and holidays
    By mrnuce in forum Excel Formulas & Functions
    Replies: 3
    Last Post: 02-19-2014, 11:23 AM
  2. [SOLVED] Shading weekends/holidays
    By kurtis.fafard in forum Excel General
    Replies: 11
    Last Post: 11-12-2013, 05:48 PM
  3. Replies: 1
    Last Post: 06-04-2009, 03:43 PM
  4. Adding weekends and holidays
    By nikita in forum Excel Formulas & Functions
    Replies: 2
    Last Post: 06-24-2008, 01:18 PM
  5. [SOLVED] Schedule to exclude weekends and holidays
    By Erin D. in forum Excel General
    Replies: 3
    Last Post: 03-15-2005, 06:06 PM

Tags for this Thread

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts

Search Engine Friendly URLs by vBSEO 3.6.0 RC 1