Optimizing Production Schedule

  1. #1
    Registered User
    Join Date
    09-26-2019
    Location
    Toronto, Canada
    MS-Off Ver
    2017
    Posts
    8

    Optimizing Production Schedule

    I was wondering if I could use Solver to help me rearrange a schedule after it is manually filled out? My issue is how complicated the schedule is going to be. The situation simplified is basically:
    - There are 6 different "mixing" machines that produce a "bulk" material in batches, usually taking around 6-8 hours
    - There are 4 different filling machines that put these bulks into different packaging
    - All 6 of the mixers can feed any of the 4 fillers
    - The optimal condition would be for the fillers to be continuously running, which means all of the mixers need to scheduled in a way that they will be able to feed the fillers to do so
    - Depending on the products being made (duration times are pulled using INDEX and MATCH from another sheet) fill and make times vary

    I was thinking of creating a column to determine the amount of down time for the fillers, sum this up at the bottom, and have solver minimize the amount of downtime. However, I don't know what variables I would let it change, and whether solver can indicate to the user how they need to rearrange the schedule.

    *Tried to upload a picture but it wouldn't work

    Thank you!

  2. #2
    Forum Expert Pepe Le Mokko's Avatar
    Join Date
    05-14-2009
    Location
    Belgium
    MS-Off Ver
    O365 v 2402
    Posts
    13,446

    Re: Optimizing Production Schedule

    Welcome to the forum

    Please attach a sample workbook (not a picture or pasted copy). Make sure there is just enough data to demonstrate your need. Include a BEFORE sheet and an AFTER sheet in the workbook if needed to show the process you're trying to complete or automate. Make sure your desired results are shown, mock them up manually if necessary.

    Remember to desensitize the data.

    Click on GO ADVANCED and then scroll down to Manage Attachments to open the upload window.

+ Reply to Thread

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Similar Threads

  1. [SOLVED] Production Schedule as per Available Manpower
    By Rajeshkumar R in forum Excel Programming / VBA / Macros
    Replies: 21
    Last Post: 08-10-2017, 02:36 AM
  2. Production Schedule
    By Hector_Soto in forum Excel General
    Replies: 11
    Last Post: 02-16-2017, 01:58 AM
  3. Schedule production help
    By liamsnodden in forum Excel Programming / VBA / Macros
    Replies: 0
    Last Post: 12-10-2012, 12:53 PM
  4. Help: Production schedule on workday
    By led.dhany in forum Excel General
    Replies: 0
    Last Post: 10-20-2012, 07:02 PM
  5. Networkdays in Production Schedule
    By gibbsmachine in forum Excel General
    Replies: 2
    Last Post: 07-02-2009, 01:44 PM
  6. optimizing task in a production schedule
    By Yeb in forum Excel Formulas & Functions
    Replies: 0
    Last Post: 03-29-2005, 02:53 AM
  7. [SOLVED] how to prepare production schedule
    By MUH in forum Excel Programming / VBA / Macros
    Replies: 1
    Last Post: 03-09-2005, 01:07 AM

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts

Search Engine Friendly URLs by vBSEO 3.6.0 RC 1