Hi,
I want to add following things in excel
1. of % of work completed and
2. milestone in the attached Gantt chart.
Please advice.
Hi,
I want to add following things in excel
1. of % of work completed and
2. milestone in the attached Gantt chart.
Please advice.
Last edited by arnab0711; 02-12-2024 at 12:52 PM.
Administrative Note:
Is your forum profile showing the Excel PRODUCT that you need this to work for?
Members will tailor the solutions they offer to the Office PRODUCT (Excel, NOT Windows) that you have. Please check that your forum profile is up-to-date in this respect. If you aren't sure, in Excel go to File | Account and report what it says below the MS logo at the top of that page. If your product is for Mac, please also state this.
The three most recent Excel products are Excel 2019, Excel 2021 and MS365 - if you are using MS365, please give this name along with the version number in your profile (e.g. MS365 Version 2306). This is in the About Excel section further down the Account page.
Thanks.
Ali
Enthusiastic self-taught user of MS Excel who's always learning!
Don't forget to say "thank you" in your thread to anyone who has offered you help.
You can reward them by clicking on * Add Reputation below their user name on the left, if you wish.
Forum Rules (updated August 2023): please read them here.
Thanks,updated my profile
where do you want the % complete and whats it based on ? - not following 100% , can you give an example of how you want to show the % complete , whats it based on and also an example manually calculated
Where do you want the milestones
I just have an old gantt chart i used many many years ago , and desensitised it , so i could use on forums
it shows milestones as a separate row item, posted here so you can see how it might look , and modify your own sheet to do the same
Last edited by etaf; 02-13-2024 at 07:07 AM.
Wayne
if my assistance has helped, and only if you wish to , there is an "* Add Reputation" on the left hand side - you can add to my reputation here
If you have a solution to your thread - Please mark your thread solved do the following: >
Select Thread Tools-> Mark thread as Solved. To undo, select Thread Tools-> Mark thread as Unsolved.
Hi
Thanks for the reply,I need the % completed in following areas
1.As you may see I have inserted a new column called % completed
2.I need the the % completed conditional formatted as another colour within the duration,so for example Act001 is of 6 days and marked in blue, while my requirement is "Today" is the 3rd day and I have completed 60% of the work,I want the 3 days in another colour and 60% shown in the cell.
I hope I can explain the scenario to you.
Try, CF formula =AND(MEDIAN($C5,WORKDAY($C5,$F5*$E5-1),G$2)=G$2,$E5>0)
Great its working now
Thank You so much