Dear Experts,
Attached is the excel file which is am trying to develop as a High Level Gantt format for multiple projects. Each row represents a separate project which have different start dates and end dates. The requirements are stated below, which i hope can be achieved & this is where i need help to develop the Gantt.
In the attached file, I want each project row to be colored with some color (e.g. grey) for the entire duration of project. Additionally, I also need the Gantt to color each project row with 'green' color for the duration from start date to =TODAY() date.
So, essentially, whenever I open this Gantt, there would be 2 colors appearing on each project row. i.e. Grey color will automatically populate for the entire project duration & green color will be overlaid on this grey until today's date. Further, if the end date of project has passed by today's date, then only green color should appear for the entire project duration & not further.
The idea is to represent how much duration has been passed when viewed on any given date….Green indicates this duration until =today()
Next, in column E, I have put column header as 'FLAG", which has 2 options in drop-down, Y or N, If it is Y, then column F, header as 'FLAG MONTH' will be updated manually by giving the actual month reference which has some flag (i.e. any issue/alarm/risk etc...).Now, if this Column F is populated with any certain month, I need that specific month cell against that respective project row to be highlighted in LIGHT RED (our standard conditional formatting RAG color).
The column G, header as 'FLAG REMARKS' will also be updated manually to indicate what type of flag it is….(e.g., Utilization impact, Cost overrun, Resource risk, Delivery delay etc..)
Further, I was also looking to check if there is a way to archive the entire sheet for a specific month which has passed by. For e.g., Feb-24 last day is 29-Feb-24, so the sheet should be archived on a separate tab with name as Feb-24….so essentially, once a month is passed, all those months Gantts status should sit in separate tabs as archived & locked for editing.
This way, we can see how was the progress/flags in each of the respective months.
Hope i was able to explain myself clear. Kindly help with your suggestions/formulas.
Thanks,
Mahesh
Bookmarks