    Time to dollars

    I have a schedule that works really well to calculate how many total hours
    per employee, but when I want to add a column that multiplies the total hours
    by an rate per hour, the result isn't right--it comes out in the form of
    time. If I have a cell that results in 32:00:00 total hours and have that
    multiplied by say 7 dollars per hour the answer comes out as 224:00:00. I
    need to use the result in other labor cost calculations, but it wont' work as
    a time. Is there a way to make that into a number (e.g. 224 )? I need to be
    able to divied the 224:00:00 result by a number equal to total revenue and
    derive a percentage. Any ideas?

    Thanks people.

    Rudy

  2. #2
    Jason Morin
    Guest

    Re: Time to dollars

    =A1*7*24

    Format the cell as General.

    HTH
    Jason
    Atlanta, GA

    >-----Original Message-----
    >I have a schedule that works really well to calculate

    how many total hours
    >per employee, but when I want to add a column that

    multiplies the total hours
    >by an rate per hour, the result isn't right--it comes

    out in the form of
    >time. If I have a cell that results in 32:00:00 total

    hours and have that
    >multiplied by say 7 dollars per hour the answer comes

    out as 224:00:00. I
    >need to use the result in other labor cost calculations,

    but it wont' work as
    >a time. Is there a way to make that into a number (e.g.

    224 )? I need to be
    >able to divied the 224:00:00 result by a number equal to

    total revenue and
    >derive a percentage. Any ideas?
    >
    >Thanks people.
    >
    >Rudy
    >.
    >


  3. #3
    Atlanta Rudy
    Guest

    Re: Time to dollars

    Thanks Jason, but that only converts the first answer of 224:00:00 to
    9.3333333.

    The schedule has times entered in and out 3:00pm to 11:00pm, then sums each
    day up for a total of 32:00:00. I've made another cell do the multiplication
    of 32:00:00 x 7 (the employee's hourly rate of pay) which gives a result of
    224:00:00. Since all the results are in time, I can't divide to get a proper
    ratio. Changing the results cells format to anything else won't give me
    total time. I'm stuck in a catch 22.

    "Jason Morin" wrote:

    > =A1*7*24
    >
    > Format the cell as General.
    >
    > HTH
    > Jason
    > Atlanta, GA
    >
    > >-----Original Message-----
    > >I have a schedule that works really well to calculate

    > how many total hours
    > >per employee, but when I want to add a column that

    > multiplies the total hours
    > >by an rate per hour, the result isn't right--it comes

    > out in the form of
    > >time. If I have a cell that results in 32:00:00 total

    > hours and have that
    > >multiplied by say 7 dollars per hour the answer comes

    > out as 224:00:00. I
    > >need to use the result in other labor cost calculations,

    > but it wont' work as
    > >a time. Is there a way to make that into a number (e.g.

    > 224 )? I need to be
    > >able to divied the 224:00:00 result by a number equal to

    > total revenue and
    > >derive a percentage. Any ideas?
    > >
    > >Thanks people.
    > >
    > >Rudy
    > >.
    > >

    >


  4. #4
    Peo Sjoblom
    Guest

    Re: Time to dollars

    No you are not stuck in catch 22

    =cell_with_32:00*24*7

    formatted as general returns 224 as expected

    224:00:00 formatted as general returns 9.3333333
    you need to multiply by 24 as well

    --
    Regards,

    Peo Sjoblom

    (No private emails please, for everyone's
    benefit keep the discussion in the newsgroup/forum)



    "Atlanta Rudy" <[email protected]> wrote in message
    news:[email protected]...
    > Thanks Jason, but that only converts the first answer of 224:00:00 to
    > 9.3333333.
    >
    > The schedule has times entered in and out 3:00pm to 11:00pm, then sums
    > each
    > day up for a total of 32:00:00. I've made another cell do the
    > multiplication
    > of 32:00:00 x 7 (the employee's hourly rate of pay) which gives a result
    > of
    > 224:00:00. Since all the results are in time, I can't divide to get a
    > proper
    > ratio. Changing the results cells format to anything else won't give me
    > total time. I'm stuck in a catch 22.
    >
    > "Jason Morin" wrote:
    >
    >> =A1*7*24
    >>
    >> Format the cell as General.
    >>
    >> HTH
    >> Jason
    >> Atlanta, GA
    >>
    >> >-----Original Message-----
    >> >I have a schedule that works really well to calculate

    >> how many total hours
    >> >per employee, but when I want to add a column that

    >> multiplies the total hours
    >> >by an rate per hour, the result isn't right--it comes

    >> out in the form of
    >> >time. If I have a cell that results in 32:00:00 total

    >> hours and have that
    >> >multiplied by say 7 dollars per hour the answer comes

    >> out as 224:00:00. I
    >> >need to use the result in other labor cost calculations,

    >> but it wont' work as
    >> >a time. Is there a way to make that into a number (e.g.

    >> 224 )? I need to be
    >> >able to divied the 224:00:00 result by a number equal to

    >> total revenue and
    >> >derive a percentage. Any ideas?
    >> >
    >> >Thanks people.
    >> >
    >> >Rudy
    >> >.
    >> >

    >>




  5. #5
    Atlanta Rudy
    Guest

    Re: Time to dollars

    Thanks everybody......EVERYTHING WORKS!!!!! Now my managers who don't
    understand where the "any key" is can turn in a shcedule without a bunch of
    "VALUE" in the total fields. Thank you all very much.

    Rudy

    "Peo Sjoblom" wrote:

    > No you are not stuck in catch 22
    >
    > =cell_with_32:00*24*7
    >
    > formatted as general returns 224 as expected
    >
    > 224:00:00 formatted as general returns 9.3333333
    > you need to multiply by 24 as well
    >
    > --
    > Regards,
    >
    > Peo Sjoblom
    >
    > (No private emails please, for everyone's
    > benefit keep the discussion in the newsgroup/forum)
    >
    >
    >
    > "Atlanta Rudy" <[email protected]> wrote in message
    > news:[email protected]...
    > > Thanks Jason, but that only converts the first answer of 224:00:00 to
    > > 9.3333333.
    > >
    > > The schedule has times entered in and out 3:00pm to 11:00pm, then sums
    > > each
    > > day up for a total of 32:00:00. I've made another cell do the
    > > multiplication
    > > of 32:00:00 x 7 (the employee's hourly rate of pay) which gives a result
    > > of
    > > 224:00:00. Since all the results are in time, I can't divide to get a
    > > proper
    > > ratio. Changing the results cells format to anything else won't give me
    > > total time. I'm stuck in a catch 22.
    > >
    > > "Jason Morin" wrote:
    > >
    > >> =A1*7*24
    > >>
    > >> Format the cell as General.
    > >>
    > >> HTH
    > >> Jason
    > >> Atlanta, GA
    > >>
    > >> >-----Original Message-----
    > >> >I have a schedule that works really well to calculate
    > >> how many total hours
    > >> >per employee, but when I want to add a column that
    > >> multiplies the total hours
    > >> >by an rate per hour, the result isn't right--it comes
    > >> out in the form of
    > >> >time. If I have a cell that results in 32:00:00 total
    > >> hours and have that
    > >> >multiplied by say 7 dollars per hour the answer comes
    > >> out as 224:00:00. I
    > >> >need to use the result in other labor cost calculations,
    > >> but it wont' work as
    > >> >a time. Is there a way to make that into a number (e.g.
    > >> 224 )? I need to be
    > >> >able to divied the 224:00:00 result by a number equal to
    > >> total revenue and
    > >> >derive a percentage. Any ideas?
    > >> >
    > >> >Thanks people.
    > >> >
    > >> >Rudy
    > >> >.
    > >> >
    > >>

    >
    >
    >


+ Reply to Thread

Thread Information

Users Browsing this Thread

There are currently 1 users browsing this thread. (0 members and 1 guests)

Bookmarks

Posting Permissions

  • You may not post new threads
  • You may not post replies
  • You may not post attachments
  • You may not edit your posts

Search Engine Friendly URLs by vBSEO 3.6.0 RC 1